Table of contents

Page

EXECUTIVE SUMMARY.. 1

Introduction. 1

Summary of Main Works Undertaken and Key Measures Implemented. 1

Environmental Monitoring Works. 1

Key Information in the Reporting Month. 4

Reporting Changes. 4

Future Key Issues. 4

1      INTRODUCTION.. 5

Background. 5

Purpose of the Report 6

Project Organizations. 6

Construction Activities undertaken during the Reporting Month. 6

Summary of EM&A Requirements. 7

Status of Environmental Licensing and Permitting. 7

2      AIR Quality.. 8

Monitoring Requirement 8

Monitoring Locations. 8

Monitoring Parameters and Frequency. 8

Monitoring Equipment 9

Monitoring Methodology. 9

Results and Observations. 11

Comparison of EM&A Result with EIA Prediction. 12

3      noise.. 15

Monitoring Requirements. 15

Monitoring Locations. 15

Monitoring Parameters, Frequency and Duration. 15

Monitoring Equipment 16

Monitoring Methodology and QA/QC Procedure. 16

Maintenance and Calibration. 16

Results and Observations. 17

Comparison of EM&A Result with EIA Prediction. 18

4      Water quality.. 19

Monitoring Requirement 19

5      waste management.. 19

6      ecology.. 20

7      fisheries. 20

8      Cultural heritage.. 20

9      Landscape and visual impact.. 21

10    Landfill gas monitoring.. 21

Monitoring Requirement 21

11    HAZARD TO LIFE.. 21

12    ENVIRONmental audit.. 22

Site Audits. 22

Implementation Status of Environmental Mitigation Measures. 22

Implementation Status of Event and Action Plans. 23

13    Environmental non-conformance.. 23

Summary of Complaint, Warning, Notification of any Summons and Successful Prosecution. 23

Summary of Exceedance. 23

14    future Key issues. 23

Monitoring Schedule. 23

Conclusions and recommendations. 24

Conclusions. 24

Recommendations. 24

 

lIST OF TABLES

 

Table I            Non-compliance (exceedance) Record for the Project in the Reporting Month

Table II           Monthly Complaints, Notifications of Summons and Successful Prosecutions in the Reporting Month

Table III          Summary of Complaints Details in Reporting Month

Table IV          Summary Table for Site Activities in the next Reporting Period

Table 1.1         Key Project Contacts

Table 1.2         Summary of Environmental License and Permit

Table 2.1         Air Quality Monitoring Locations

Table 2.2         Frequency and Parameters of Air Quality Monitoring

Table 2.3         Air Quality Monitoring Equipment

Table 2.4         Major Dust Source during Air Quality Monitoring

Table 2.5         Comparison of 1-hr TSP Monitoring Data with Predictions in EIA Report

Table 2.6         Comparison of 24-hr TSP Monitoring Data with Predictions in EIA Report

Table 3.1         Noise Monitoring Stations

Table 3.2         Frequency and Parameters of Noise Monitoring

Table 3.3        Noise Monitoring Equipment

Table 3.4         Other Noise Source Identified during Noise Monitoring

Table 3.5         Baseline Noise Level and Noise Limit Level for Monitoring Stations

Table 3.6         Maximum Predicted Mitigated Construction Noise Levels in EIA Report

Table 10.1       Landfill Gas Monitoring Equipment (not used)

Table 12.1       Observations and Recommendations of Site Audit

 

 

 

 

 

lIST OF FIGUREs

 

Figure 1           Site Layout Plan

Figure 1.2        Organizational Structure for Environmental Management

Figure 2           Locations of Air Quality and Construction Noise Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix A    Action and Limit Levels

Appendix B    Copies of Calibration Certificates

Appendix C    Weather Information

Appendix D    Environmental Monitoring Schedules

Appendix E     1-hour TSP Monitoring Results and Graphical Presentations

Appendix F     24-hour TSP Monitoring Results and Graphical Presentations

Appendix G    Noise Monitoring Results and Graphical Presentations

Appendix H    Waste Generation in the Reporting Month

Appendix I      Site Audit Summary

Appendix J      Environmental Mitigation Implementation Schedule (EMIS)

Appendix K    Record of Landfill Gas Monitoring by Contractor (not used)

Appendix L     Event and Action Plans

Appendix M   Summaries of Environmental Complaint, Warning, Summon and Notification of Successful Prosecution

Appendix N    Summary of Exceedance

Appendix O    Tentative Construction Programme

                       

 

 

 


EXECUTIVE SUMMARY

Introduction

 

1.             This is the 31th Environmental Monitoring and Audit (EM&A) Report prepared by the Environmental Team (ET), Cinotech Consultants Ltd., for Contract No. ED/2018/04 Trunk Road T2 and Infrastructure Works for Developments at the Former South Apron. This report summarized the monitoring results and audits findings of the EM&A programme under the issued Environmental Permit (EP) No. EP-458/2013/C and in accordance with the EM&A Manual (AEIAR-173/2013) during the reporting month of November 2022.

Summary of Main Works Undertaken and Key Measures Implemented

 

2.      The main works undertaken during the reporting period are as follows:

 

·         East Bound RC Structure Construction, Service Gallery Drill & Blast, Service Gallery A Installation.

·         East Ventilation Building WB Blinding & Waterproofing and RC Structure.

·         West Bound Extension & Blast Tunnel, RC Structure Construction. 

 

3.      Implementation of the key mitigation measures during the reporting period are as follows:

 

      Construction Noise

·           Construction activities were scheduled to minimize noise nuisance to the nearby sensitive receiver.

·           Use of Quality Powered Mechanical Equipment (QPME) on site.

·           Erected the noise barrier on site.

       Air Quality

·         Regularly watering on site to avoid dust generation.

       Landscape and Visual

·         Tree protection zones were fenced off to protect the existing trees on site.

Environmental Monitoring Works

 

4.      Environmental monitoring for the Project was performed in accordance with the EM&A Manual and the monitoring results were checked and reviewed. Site Inspections/Audits were conducted once per week. The implementation of the environmental mitigation measures, Event Action Plans and environmental complaint handling procedures were also checked.

 

5.      Summary of the non-compliance (exceedance) in the reporting month for the Project is tabulated in Table I.

 

 

 

Table I       Non-compliance (exceedance) Record for the Project in the Reporting Month

Environmental Monitoring

No. of Non-compliance (Exceedance)

No. of Non-compliance (Exceedance)

due to Construction Activities of this Project

Action Taken

Action Level

Limit Level

Action Level

Limit Level

Air Quality

0

0

0

0

N/A

Noise

0

0

0

0

N/A

Marine Water Quality

N/A

N/A

N/A

N/A

N/A

Groundwater Level Monitoring (Piezometer Monitoring)

N/A

N/A

N/A

N/A

N/A

Ecological

N/A

N/A

N/A

N/A

N/A

Cultural Heritage

N/A

N/A

N/A

N/A

N/A

Landfill Gas

N/A(1)

N/A

N/A(1)

N/A

N/A

Note: (1): No Action Level for Landfill Gas Monitoring.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Air Quality Monitoring

 

6.      No Action/Limit Level exceedance for 1-hour TSP monitoring was recorded.

 

7.      No Action/Limit Level exceedance was recorded for 24-hour TSP monitoring in the reporting month.

 

Construction Noise Monitoring

 

8.      No Action Level exceedance was recorded due to documented complaint in the reporting month. The Summary of Documented Complaints in the Reporting Month is tabulated in Table III.

 

9.      No Limit Level exceedance for day time construction noise monitoring were recorded in the reporting month. Detail shall refer to Appendix N.

 

Water Quality Monitoring

 

10.  Groundwater quality monitoring had been suspended since October 2019 upon the agreement by EPD. Further details should be founded at Section 4.1.

 

11.  No marine water quality monitoring is required as no marine works will be conducted at the Cha Kwo Ling and Lam Tin areas for this project.

 

12.  As the construction activity is approximately 120m away from the piezometer gate, no piezometer monitoring is required.

 

 

Waste Management 

 

13.  Wastes generated from this Project include inert construction and demolition (C&D) materials, and non-inert C&D materials. Details of waste management data is presented in Appendix H.

Ecological Monitoring

 

14.  No coral monitoring is required as no marine works will be conducted at the Cha Kwo Ling and Lam Tin areas for this project.

 

Fisheries Impact Monitoring

 

15.  No specific fisheries monitoring programme is required during the construction phase.

 

Monitoring on Cultural Heritage

 

16.  As the construction works of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to the TKOLTT at the Eastern Ventilation Building are located more than 100m away from the Cha Kwo Ling Tin Hau temple, no monitoring on cultural heritage is required.

 

Landscape and Visual Monitoring and Audit

 

17.  The implementation of landscape and visual mitigation measures was checked by a registered landscape architect. Recommended follow-up actions have been discharged by the Contractor.  Details of the audit findings and implementation status are presented in Section 12.

 

Landfill Gas Monitoring

 

18.  Monitoring of landfill gases was commenced in December 2016. Since no excavation activity for this Project was carried out within the Sai Tso Wan Landfill Consultation Zone in the reporting month, no landfill gas monitoring is required

 

Hazard to Life Monitoring

 

19.   No environmental monitoring and audit is required as no hazard assessment was conducted.

 

Environmental Site Inspection

 

20.  Joint weekly site inspections were conducted by representatives of the Contractor, Engineer and Environmental Team. Details of the audit findings and implementation status are presented in Section 12.


 

Key Information in the Reporting Month

 

21.  Summary of key information in the reporting month is tabulated in Table II

                                                                                                                             

Table II    Summary of Complaints, Notifications of Summons and Successful Prosecutions in the Reporting Month

Event

Event Details

Action Taken

Status

Number

Nature

Complaints Received

0

--

N/A

N/A

Notifications of any summons & prosecutions received

0

--

N/A

N/A

 

 

 

 

 

 

 

22.  Summary of complaints received in the reporting month is tabulated in Table III.

 

Table III     Summary of Complaints Details in Reporting Month

 

Complaint Type

Investigation Findings

Follow-up Action / Mitigation Measure

-

-

-

 

Reporting Changes

23.  No reporting change is recorded in the reporting months.

 

Future Key Issues

 

24.  The key works or activities will be anticipated in the next reporting period are as follows:

 

 Table IV    Summary Table for Site Activities in the next Reporting Period

Site Activities (November 2022)

Key Environmental Issues

1.       East Bound RC Structure Construction, Service Gallery Frill & Blast. Service Gallery A Installation

2.       East Ventilation Building WB Blinding & Waterproofing, RC Structure

3.       West Bound Extension & Blast Tunnel, RC Structure Construction

(A) / (B) / (C) / (D)

Note:

(A)    Dust generation from haul road, stockpile of dusty materials, exposed site area, excavation works and rock breaking activities;

(B)    Noisy construction activity such as rock-breaking activities and piling works;

(C)    Runoff from exposed slope or site area; and

(D)    Wastewater and runoff discharge from site.


 

1               INTRODUCTION

Background

1.1         In 2009, Civil Engineering and Development Department (CEDD) commissioned a Kai Tak Development (KTD) Trunk Road T2 and Infrastructure at South Apron Investigation. The assignment covers the provision of the Trunk Road T2 and its connections with the Central Kowloon Route (CKR) at the north apron area and the Tseung Kwan O Lam Tin Tunnel (TKOLTT) to the south in the Cha Kwo Ling area.

1.2         The Trunk Road T2 Project is one of the designated Projects under Schedule 2 of the EIAO proposed in the KTD. CEDD submitted the Project Profile (No. PP-379/2009) on 24 March 2009 for application for an EIA study brief for the Trunk Road T2 Project under the EIAO. Accordingly, an EIA Study Brief (ESB-203/2009) for the Trunk Road T2 Project was issued on 30 April 2009. The Environmental Impact Assessment (EIA) Report for the Trunk Road T2 Project was approved under the Environmental Impact Assessment Ordinance (EIAO) on 19 September 2013. The corresponding Environmental Permit (EP) was issued on 19 September 2013 (EP no.: EP-451/2013).

1.3         The Contract No. ED/2018/04 is the main contract of Trunk Road T2 (T2 Main Works) which comprises mainly the design and construction of a dual two-lane trunk road of approximately 3.0km long with about 2.7km of the trunk road in form of tunnel; ventilation and administration buildings, environmental protection and mitigation works and etc. The EM&A programme under this Contract is governed by the two EPs (EP-451/2013 and EP-458/2013/C) and two EM&A Manuals (AEIAR-174/2013 and AEIAR-173/2013). The work areas of the T2 Main Works are shown in Figure 1 and the works to be executed under this Contract and corresponding EPs are summarized as follows:

Environmental Permit

Works Description

EP-451/2013 Trunk Road T2

Trunk Road T2

·     Construction of highway and sub-sea tunnel connecting between Central Kowloon Route and Cha Kwo Ling Tunnel

·     Western & Eastern Ventilation Buildings

EP-458/2013/C Tseung Kwan O Lam Tin Tunnel (TKOLTT) and Associated Works

Cha Kwo Ling Tunnel

Construction of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to the TKOLTT at the Eastern Ventilation Building

 

Monitoring Works in Lam Tin under EP-458/2013/C

1.4         Under Agreement No. CE 59/2015 (EP) Tseung Kwan O Lam Tin Tunnel (TKOLLT) and Associated Works, the baseline monitoring works in Lam Tin under the EM&A Manual (AEIAR-173/2013) were conducted by the Environmental Team (ET) for the Agreement No. CE 59/2015 (EP) at the approved monitoring locations, namely AM1, AM2, AM3, AM4, AM4 (A) CM1, CM2, CM3, CM4 and CM5. Impact monitoring within the Lam Tin area shall be conducted by the ET of Contract No. ED/2018/04 upon cessation of Agreement No. CE 59/2015 (EP). The data obtained from the impact monitoring works completed by the ET of Agreement No. CE 59/2015 (EP) will be adopted in this report.


 

1.5         Cinotech Consultants Ltd. was designated as the Environmental Team (ET) to undertake the EM&A works for Trunk Road T2 and Infrastructure Works for Developments at the Former South Apron (hereinafter called the Project). 

Purpose of the Report

1.6         This is the 31th Monthly EM&A Report which summarises the impact monitoring results and audit findings for the EM&A programme during the reporting period in November 2022.

Project Organizations

1.7         Different Parties with different levels of involvement in the Project organization include:

·         Permit Holder Civil Engineering and Development Department  (CEDD)

·         Supervisor Representative Hyder-Meinhardt Joint Venture (HMJV)

·         Environmental Team (ET) Cinotech Consultants Limited (Cinotech)

·         Independent Environmental Checker (IEC) Ramboll Hong Kong Limited (Ramboll)

·         Contractor Bouygues Travaux Publics (BTP)

1.8         The key contacts of the Project are shown in Table 1.1.

Table 1.1       Key Project Contacts

Party

Role

Contact Person

Phone No.

CEDD

Permit Holder

Mr. Wong Chi Wai, Tommy

3842 7111

HMJV

Supervisor Representative

Ms. Hazel Tang

2149 8524

Cinotech

Environmental Team

Mr. KS Lee (ETL)

2151 2091

Ms. Karina Chan

2157 3880

Ramboll

Independent Environmental Checker

Mr. YH Hui

3465 2850

BTP

Contractor

Mr. Marcus Cheung

6628 2685

 

1.9         The Organizational Structure for Environmental Management is shown in Figure 1.2.

Construction Activities undertaken during the Reporting Month

1.10     The major site activities undertaken in the reporting month included:

·         East Bound RC Structure Construction, Service Gallery Drill & Blast, Service Gallery A Installation.

·         East Ventilation Building WB Blinding & Waterproofing and RC Structure.

·         West Bound Extension & Blast Tunnel, RC Structure Construction. 

 

Summary of EM&A Requirements

1.11     The EM&A programme requires construction noise, air quality monitoring and environmental site audit, etc. The EM&A requirements for each parameter are described in the following sections, including:

·         All monitoring parameters;

·         Action and Limit levels for all environmental parameters;

·         Event Action Plans;

·         Environmental mitigation measures, as recommended in the Project EIA Report.

1.12     The advice on the implementation status of environmental protection and pollution control/mitigation measures is summarized in Section 12 of this report.

1.13     This report presents the monitoring results, observations, locations, equipment, period, methodology and QA/QC procedures of the monitoring parameters of the required environmental monitoring works and audit works for the Project in November 2022.

Status of Environmental Licensing and Permitting

1.14     All permits/licenses obtained for the Project are summarized in Table 1.2.

Table 1.2      Summary of Environmental License and Permit

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-451/2013

19 Sep 2013

N/A

Valid

EP-458/2013/C

20 Jan 2017

N/A

Valid

Notification pursuant to Air Pollution (Construction Dust) Regulation

Ref. No.: 451120

20 Nov 2019

N/A

Valid

Billing Account for Construction Waste Disposal

A/C No.: 7036016

09 Dec 2019

N/A

Valid

Construction Noise Permit

CNP No. (For Portion Q): GW-RE0919-22

23 Sep 2022

23 Mar 2023

Valid

CNP No. (For Portion T1): GW-RE0997-22

6 Oct 2022

23 Dec 2022

Valid

Wastewater Discharge License

WT00036699-2020

14 Jan 2021

31 Jan 2026

Valid

Chemical Waste Producer License

WPN: 5213-286-B2557-03

09 Mar 2020

N/A

Valid

 


2               AIR Quality

Monitoring Requirement

2.1         According to Section 2.2.4 of the EM&A Manual (AEIAR-173/2013), 1-hour and 24-hour Total Suspended Particulates (TSP) monitoring was conducted to monitor the air quality for this Project. For regular impact monitoring, a sampling frequency of at least once in every six days at all of the monitoring stations for 1-hour and 24-hour TSP monitoring. Appendix A shows the established Action/Limit Levels for the environmental monitoring works.

Monitoring Locations

2.2         Five designated monitoring stations were selected for air quality monitoring programme. Table 2.1 describes the air quality monitoring locations, which are also depicted in Figure 2.

Table 2.1  Air Quality Monitoring Locations

Monitoring Stations

Location

Location of Measurement

AM1

Tin Hau Temple

Ground Level

AM2

Sai Tso Wan Recreation Ground

Ground Level

AM3

Yau Lai Estate Bik Lai House

Rooftop (41/F)

AM4(1)

Sitting-out Area at Cha Kwo Ling Village

Ground Level

AM4(B)(2) (*)(**)

Flat 103 Cha Kwo Ling Village

Ground Level

Remarks:

(1) For 1-hour TSP monitoring;

(2) For 24-hour TSP monitoring

(*) Air quality monitoring at designated station AM4 (24-hr TSP) was rejected by the premise owners.

     Therefore, baseline and impact air quality monitoring works were carried out at alternative air quality monitoring stations AM4 (A) (24-hr TSP only)

(**) AM4(A) is not available for conducing monitoring due to the demolition of administrative office.

Monitoring Parameters and Frequency

2.3         Table 2.2 summarizes the monitoring parameters, monitoring period and frequencies of impact air quality monitoring. The monitoring schedule is shown in Appendix D.

          Table 2.2 Frequency and Parameters of Air Quality Monitoring

Monitoring Stations

Parameter

Period

Frequency

AM1, AM2, AM3, AM4

1-hour TSP

0700 1900

3 times per 6 days

AM1, AM2, AM3, AM4(B)

24-hour TSP

24 hours

Once every 6 days

 

 


 

Monitoring Equipment

2.4         High Volume Samplers (HVS) in compliance with the specification stipulated in the EM&A Manual (AEIAR-173/2013), Section 2.3.1, were used to carry out 24-hour TSP monitoring. Direct reading dust meter were also used to measure 1-hour average TSP levels. The 1-hour sampling was determined by HVS to check the validity and accuracy of the results measured by direct reading method.

2.5         Wind data monitoring equipment was set at rooftop (about 41/F) of Yau Lai Estate Bik Lai House for logging wind speed and wind direction such that the wind sensors are clear of obstructions or turbulence caused by building. The wind data monitoring equipment is re-calibrated at least once every six months and the wind directions are divided into 16 sectors of 22.5 degrees each. The location is shown in Figure 2. This weather information for the reporting month is summarized in Appendix C.

2.6         Table 2.3 summarizes the equipment used for air quality monitoring by the ET for Contract No. CE 59/2015 (EP). Copies of calibration certificates are attached in Appendix B.

Table 2.3         Air Quality Monitoring Equipment

Equipment

Model

Quantity

1-hour TSP Dust Meter

Sibata Model No. LD-5R

(Serial No.: 972781, 972778, 972779, 972780, 8Y2373, 8Y2374)

Sibata Model No. LD-3B

(Serial No.2Y6194)

7

HVS Sampler

GMW model: GS2310

(Serial No.: 1287, 10379, 10599)

3

TE 5170 (Serial No.: 1956)

1

Calibrator

TISCH Model: TE-5025A

(Serial No.: 3864)

1

Wind Anemometer

Davis Weather Monitor II, Model no. 7440

(Serial No.: MC01010A44)

1

 

Monitoring Methodology

1-hour TSP Monitoring

Measuring Procedures

2.7         The measuring procedures of the 1-hour dust meter are in accordance with the Manufacturers Instruction Manual as follows:

(Sibata Model No.: LD-5R)

·           The 1-hour dust meter is placed at least 1.3 meters above ground.

·           Set POWER to ON and make sure that the battery level was not flash or in low level.

·           Allow the instrument to stand for about 3 minutes and then the cap of the air sampling inlet has been released.

·           Push the knob at MEASURE position.

·            Set time/mode setting to [BG] by pushing the time setting switch.  Then, start the background measurement by pushing the start/stop switch once.  It will take 6 sec. to complete the background measurement.

·            Push the time setting switch to change the time setting display to [MANUAL] at the bottom left of the liquid crystal display. Finally, push the start/stop switch to stop the measuring after 1 hour sampling.

·           Information such as sampling date, time, count value and site condition were recorded during the monitoring period.

 

Maintenance/Calibration

2.8         The following maintenance/calibration is required for the 1-hour dust meter:

·           Check and calibrate the meter by HVS to check the validity and accuracy of the results measured by direct reading method at 2-month intervals throughout all stages of the air quality monitoring.

 

24-hour TSP Monitoring

Instrumentation

2.9         High volume samplers (HVS) (TISCH Model: TE-5170 and GMW Model: GS2310) completed with appropriate sampling inlets were employed for 24-hour TSP monitoring.  The sampler was composed of a motor, a filter holder, a flow controller and a sampling inlet and its performance specification complied with that required by USEPA Standard Title 40, Code of Federation Regulations Chapter 1 (Part 50).

2.10     The positioning of the HVS samplers are as follows:

·            A horizontal platform with appropriate support to secure the samplers against gusty wind shall be provided;

·            No two samplers shall be placed less than 2 meter apart;

·            The distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;

·            A minimum of 2 metres of separation from walls, parapets and penthouses is required for rooftop samplers;

·            A minimum of 2 metres of separation from any supporting structure, measured horizontally is required;

·            No furnace or incinerator flue is nearby;

·            Airflow around the sampler is unrestricted;

·            The sampler is more than 20 metres from the dripline;

·            Any wire fence and gate, to protect the sampler, shall not cause any obstruction during monitoring;

·            Permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and

·            A secured supply of electricity is needed to operate the samplers.

Operating/analytical procedures for the operation of HVS

2.11     Operating/analytical procedures for the air quality monitoring are highlighted as follows:

·           Prior to the commencement of the dust sampling, the flow rate of the high volume sampler was properly set (between 0.6 m3/min. and 1.7 m3/min.) in accordance with the EM&A manual (AEIAR-173/2013). The flow rate shall be indicated on the flow rate chart.

·           For TSP sampling, fiberglass filters with a collection efficiency of > 99% for particles of 0.3μm diameter were used.

·           The power supply was checked to ensure the sampler worked properly.  On sampling, the sampler was operated for 5 minutes to establish thermal equilibrium before placing any filter media at the designated air monitoring station.

·           The filter holding frame was then removed by loosening the four nuts and a weighted and conditioned filter was carefully centered with the stamped number upwards, on a supporting screen.

·           The filter was aligned on the screen so that the gasket formed an airtight seal on the outer edges of the filter.  Then the filter holding frame was tightened to the filter holder with swing bolts. The applied pressure should be sufficient to avoid air leakage at the edges.

·           The shelter lid was closed and secured with the aluminum strip.

·           The timer was then programmed.  Information was recorded on the record sheet, which included the starting time, the weather condition and the filter number (the initial weight of the filter paper can be found out by using the filter number).

·           After sampling, the filter was removed and sent to the HOKLAS laboratory (ALS Technichem (HK) Pty Ltd.) for weighing.  The elapsed time was also recorded.

·           Before weighing, all filters were equilibrated in a conditioning environment for 24 hours. The conditioning environment temperature should be between 25°C and 30°C and not vary by more than ±3°C; the relative humidity (RH) should be < 50% and not vary by more than ±5%. A convenient working RH is 40%.

 

Maintenance/Calibration

2.12     The following maintenance/calibration is required for the HVS:

·           The high volume motors and their accessories were properly maintained. Appropriate maintenance such as routine motor brushes replacement and electrical wiring checking were made to ensure that the equipment and necessary power supply are in good working condition.

High volume samplers were calibrated at bi-monthly intervals using TE-5025A Calibration Kit throughout all stages of the air quality monitoring.

 

Results and Observations

2.13     The impact monitoring works for air quality monitoring locations AM1, AM2, AM3 and AM4 are completed by the ET of Agreement No. CE 59/2015 (EP), and the data will be adopted in this report. As the proposal for relocation approved, the monitoring at AM4(A) will conducted at AM4(B). For the time being, as the station CKL2 for the 24 hr TSP monitoring, carried out under EM&A works for Trunk Road T2 Project (EP- 451/2013), is located in close proximity to AM4(B); the results from CKL2 are adopted as reference for the 24 TSP monitoring at AM4(B), which has similar environment when compared with that for CKL2. The location of monitoring station CKL2 is shown in Figure 2.

2.14     The impact air quality monitoring was conducted at all five monitoring stations as scheduled. The monitoring schedule is shown in Appendix D.

2.15     No Action/ Limit Level exceedance was recorded for 24-hour TSP monitoring in the reporting month.

2.16     No Action/ Limit Level exceedance was recorded for 1-hour TSP monitoring in the reporting month.

2.17     The monitoring data and graphical presentations of 1-hour and 24-hour TSP monitoring results are shown in Appendix E and Appendix F respectively.

2.18     According to field observations by ET for Agreement No. CE 59/2015 (EP) in the reporting period, the major dust source identified at the designated air quality monitoring stations are as follows:

 

Table 2.4   Major Dust Source during Air Quality Monitoring

Monitoring Stations

Major Dust Source

AM1 Tin Hau Temple

Road Traffic at Cha Kwo Ling Road, non-project related influence and the construction activity from other construction site

AM2 Sai Tso Wan Recreation Ground

Road Traffic along Sin Fat Road

AM3 Yau Lai Estate Bik Lai House

Road Traffic near Eastern Cross Harbour Tunnel Toll Plaza, non-project related influence and the construction activity from other construction site

AM4 - Sitting-out Area at Cha Kwo Ling Village

Road Traffic at Cha Kwo Ling Road

AM4(B) (**) - Flat 103 Cha Kwo Ling Village

Road Traffic at Cha Kwo Ling Road(*)

(*): Field observation observed at CKL2 during monitoring is presented. Detail refer to S2.13.

 

(**) AM4(A) is not available for conducing monitoring due to the demolition of administrative office.

 

 

Comparison of EM&A Result with EIA Prediction

2.19     The air monitoring data was compared with the predictions (with the assessment height of 1.5 mAG) in Table 3.17 of EIA Report, AEIAR-173/2013 (as approved in 2013) as summarised in Table 2.5 and Table 2.6.

 

Table 2.5     Comparison of 1-hr TSP Monitoring Data with Predictions in EIA Report

Monitoring Stations

ASR ID

Predicted Maximum 1-hr TSP Concentration in EIA Report (AEIAR-173/2013), μg/m3

Maximum 1-hr TSP Concentration in the Reporting Month
 (November 2022),
μg/m3

AM1 Tin Hau Temple

CL1

707

197.5

AM2 Sai Tso Wan Recreation Ground

CL6

266

81.9

AM3 Yau Lai Estate Bik Lai House

CL9

507

150.0

AM4 - Sitting-out Area at Cha Kwo Ling Village

CL16

430

152.5

 

Table 2.6     Comparison of 24-hr TSP Monitoring Data with Predictions in EIA Report

Monitoring Stations

ASR ID

Predicted Maximum 24-hr TSP Concentration in EIA Report (AEIAR-173/2013), μg/m3

Maximum 24-hr TSP Concentration in the Reporting Month
 (November 2022),
μg/m3

AM1 Tin Hau Temple

CL1

199

156.8

AM2 Sai Tso Wan Recreation Ground

CL6

109

57.4

AM3 Yau Lai Estate Bik Lai House

CL9

123

30.4

AM4(B) Flat 103 Cha Kwo Ling Village (*)

N/A(1)

N/A(1)

200.2 (**)

Remarks:

(1)     No 24-hr TSP concentration was predicted in EIA Report (AEIAR-173/2013)

(*) Air quality monitoring at designated station AM4 (24-hr TSP) was rejected by the premise owners. Therefore, baseline and impact air quality monitoring works were carried out at alternative air quality monitoring stations AM4 (B) (24-hr TSP only)

(**): Monitoring results at CKL2 is presented. Detail refer to S2.13

 

 

 

2.20     In the reporting month, the 1-hour TSP concentrations at AM1, AM2, AM3 and AM4 were lower than the prediction in the EIA Report, AEIAR-173/2013 (as approved in 2013). No Action/Limit level exceedance was recorded in the reporting period.

2.21     In the reporting month, the 24-hour TSP concentrations at AM1, AM2 and AM3 were lower than the prediction in the EIA Report, AEIAR-173/2013 (as approved in 2013). No Action / Limit Level exceedance was recorded for 24-hour TSP monitoring in the reporting month.


3               noise

Monitoring Requirements

3.1         According to Section 3.2.1 of the EM&A Manual (AEIAR-173/2013), construction noise monitoring was conducted to monitor the construction noise arising from the construction activities. The regular monitoring frequency for each monitoring station shall be on a weekly basis and conduct one set of measurements between 0700 and 1900 hours on normal weekdays. Appendix A shows the established Action and Limit Levels for the environmental monitoring works.

Monitoring Locations

3.2         Noise monitoring was conducted at five designated monitoring stations, namely CM1, CM2, CM3, CM4 and CM5 in the reporting period. Table 3.1 and Figure 2 show the locations of these stations.

Table 3.1   Noise Monitoring Stations

Monitoring Stations

Location

Location of Measurement

CM1

Nga Lai House, Yau Lai Estate Phase 1, Yau Tong

Rooftop (41/F)

CM2

Bik Lai House, Yau Lai Estate Phase 1, Yau Tong

Rooftop (41/F)

CM3

Block S, Yau Lai Estate Phase 5, Yau Tong

Rooftop (40/F)

CM4

Tin Hau Temple, Cha Kwo Ling

Ground Level

CM5

CCC Kei Faat Primary School, Yau Tong

Rooftop (6/F)

 

Monitoring Parameters, Frequency and Duration

3.3         Table 3.2 summarizes the monitoring parameters, frequency and total duration of monitoring.  The noise monitoring schedule is shown in Appendix D.

         Table 3.2         Frequency and Parameters of Noise Monitoring

Monitoring Stations

Time Period

Duration

Frequency

Parameter

Measurement

CM1

0700-1900 hrs on normal weekdays

30 minutes

Once per week

L10(30 min.) dB(A)

 

L90(30 min.) dB(A)

 

Leq(30 min.) dB(A)

Façade Measurement

CM2

Façade Measurement

CM3

Façade Measurement

CM4

Façade Measurement

CM5

Façade Measurement

Monitoring Equipment

3.4         Integrating Sound Level Meter was used for impact noise monitoring. The meters were Type 1 sound level meter capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx) that also complied with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Table 3.3 summarizes the noise monitoring equipment being used by the ET for Agreement No. CE 59/2015 (EP) within the reporting period. Copies of calibration certificates are attached in Appendix B.

Table 3.3        Noise Monitoring Equipment

Equipment

Model

Quantity

Integrating Sound Level Meter

BSWA 308 (Serial No.: 580287,580156)

2

Calibrator

ST-120 (Serial No.: 181001608, 181001637)

2

Monitoring Methodology and QA/QC Procedure

3.5         The monitoring procedures are as follows:

·              The monitoring station was normally be at a point 1m from the exterior of the sensitive receivers building façade and be at a position 1.2m above the ground.

·              For free field measurement, the meter was positioned away from any nearby reflective surfaces. All records for free field noise levels were adjusted with a correction of +3 dB(A).

·              The battery condition was checked to ensure the correct functioning of the meter.

·              Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:

-            Frequency weighting: A

-            Time weighting: Fast

-            Time measurement: 30 minutes

·              Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94.0 dB at 1000 Hz.  If the difference in the calibration level before and after measurement was more than 1.0 dB, the measurement would be considered invalid and repeat of noise measurement would be required after re-calibration or repair of the equipment.

·              The wind speed was frequently checked with the portable wind meter.

·              At the end of the monitoring period, the Leq, L90 and L10 were recorded.  In addition, site conditions and noise sources were recorded on a standard record sheet.

·              Noise monitoring would be cancelled in the presence of fog, rain, and wind with a steady speed exceeding 5 m/s, or wind with gusts exceeding 10 m/s. Supplementary monitoring would be provided to ensure sufficient data would be obtained.

Maintenance and Calibration

3.6         The microphone head of the sound level meter and calibrator were cleaned with a soft cloth at quarterly intervals.

3.7         The sound level meter and calibrator were checked and calibrated at yearly intervals.

3.8         Immediately prior to and following each noise measurement the accuracy of the sound level meter was checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements were accepted as valid only if the calibration levels from before and after the noise measurement agree to within 1.0 dB.

Results and Observations

3.9         The data obtained from the impact monitoring works completed by the ET of Agreement No. CE 59/2015 (EP) will be adopted in this report. 

3.10     No Action Level exceedance was recorded due to the documented complaint in the reporting month.

3.11     No Limit Level exceedance was recorded for day-time construction noise monitoring in the reporting month.

3.12     Noise monitoring results and graphical presentations are shown in Appendix G.

3.13     According to field observations by ET for Agreement No. CE 59/2015 (EP) in the reporting period, the major noise sources identified at the noise monitoring stations are shown in Table 3.4.

Table 3.4       Other Noise Source Identified during Noise Monitoring

Monitoring Stations

Major Noise Source

CM1

Road Traffic near Eastern Cross Harbour Tunnel Toll Plaza, non-project related construction activities

CM2

Road Traffic near Eastern Cross Harbour Tunnel Toll Plaza, non-project related construction activities

CM3

Road Traffic near Eastern Cross Harbour Tunnel Toll Plaza non-project related construction activities

CM4

Road Traffic at Cha Kwo Ling Road, non-project related construction activities

CM5

Road Traffic near Eastern Cross Harbour Tunnel Toll Plaza,

Construction activity from other construction site,

Road Traffic at Yau Tong Road

                .

Table 3.5      Baseline Noise Level and Noise Limit Level for Monitoring Stations

Monitoring Stations

Baseline Noise Level, dB (A)
(at 0700
1900 hrs on normal weekdays)

Noise Limit Level, dB (A) (at 0700 1900 hrs on normal weekdays)

CM1

65.5

75

CM2

63.6

CM3

65.6

CM4

62.0