TABLE OF CONTENTS
Summary of Main Works
Undertaken and Key Measures Implemented
Environmental
Monitoring Works
Summary
of Complaint, Warning, Notification of Summons and Successful Prosecution
Reporting Changes in the
Reporting Quarter
Construction
Activities undertaken during the Report Quarter
2. ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS
Monitoring
Parameters and Monitoring Locations
Monitoring
Methodology and Calibration Details
Environmental
Quality Performance Limits (Action and Limit Levels)
Implementation Status of
Environmental Mitigation Measures
Monitoring
on Cultural Heritage
Landscape
and Visual Monitoring and Audit
Influencing
Factors on the Monitoring Results
Summary
of Environmental Complaints and Prosecutions
5. COMMENTS, CONCLUSIONS AND RECOMMENDATIONS
Review of Monitoring
Methodology and the Practicality and Effectiveness of EM&A Programme
Effectiveness of Mitigation
Measures
LIST OF TABLE
Table I Summary Table
for Non-compliance Recorded in the Reporting Quarter
Table II Summary Table
for Key Information in the Reporting Quarter
Table 1.1 Key Project
Contacts
Table 3.1 Summary of Weather Conditions in the Reporting Period
Table 3.2 Major Dust Sources during the Monitoring in the Reporting
Period
Table 3.3 Major Noise Sources during the Monitoring in the Reporting
Period
lIST OF FIGUREs
Figure 1 Site
Layout Plan
Figure 1.2 Project
Organisation for Environmental Monitoring and Audit
Figure 2 Locations of Air Quality and Construction Noise Monitoring Stations
LIST OF APPENDICES
C Graphical
Presentation of Air Quality Monitoring Results
D Graphical
Presentation of Noise Monitoring Results
E Graphical Presentation of Landfill Gas Monitoring
Results (Not used)
G Environmental Mitigation Implementation Schedule (EMIS)
J Summaries of
Environmental Complaint, Warning, Summon and Notification of Successful
Prosecution
1.
This is the 17th Quarterly Environmental Monitoring and Audit (EM&A)
Report prepared by the Environmental Team (ET), Cinotech Consultants Ltd., for
“Trunk Road T2 and Infrastructure Works at the Former South Apron”. This report
summarized the monitoring results and audits findings of the EM&A programme
under the issued Environmental Permit (EP) No. EP-458/2013/C and in accordance
with the EM&A Manual (AEIAR-173/2013) during the reporting period from May 2024 to July 2024.
2. The
construction activities undertaken in the reporting quarter were as follows:
Contract No. |
Project Title |
Reporting month |
Site Activities |
ED/2018/04 |
Trunk Road
T2 and Infrastructure Works for Developments at South Apron |
May 2024 |
1. East Bound – Wall & Crown 2. East Ventilation Building – RC Structure,
ABWF, E&M 3. West Bound – Bulkhead Construction, OHVD |
June 2024 |
1. East Ventilation Building RC Structure 2. East Ventilation Building ABWF 3. East Ventilation Building E&M 4. East Bound – Wall & Crown 5. West Bound – OHVD 6. West Bound – Bulkhead Construction |
||
July 2024 |
1. East
Ventilation Building RC Structure 2. East
Ventilation Building ABWF 3. East
Ventilation Building E&M 4. East
Bound – Wall & Crown 5. West
Bound – OHVD 6. West
Bound – Bulkhead Construction |
||
ED/2020/03 |
Trunk Road T2
- Traffic Control And Surveillance System (TCSS) and Associated Works(1) |
May 2024 – July 2024 |
N/A |
(1): No major construction work was
undertaken during reporting quarter.
3. Implementation of the key mitigation measures during the
reporting period are as follows:
Construction Noise
·
Construction
activities were scheduled to minimize noise nuisance to the nearby sensitive
receiver.
·
Use of
Quality Powered Mechanical Equipment (QPME) on site.
·
Erected the
noise barrier on site.
Air Quality
·
Regularly
watering on site to avoid dust generation.
Landscape and Visual
·
Tree
protection zones were fenced off to protect the existing trees on site.
4.
Environmental
monitoring for the Project was performed in accordance with the EM&A Manual and the monitoring results were checked and reviewed. Site Inspections/Audits were conducted once per week. The implementation of the environmental
mitigation measures, Event Action Plans and environmental complaint handling
procedures were also checked.
5. Summary of the non-compliance in the reporting
quarter for the Project is tabulated in Table
I. Details of the environmental monitoring results is presented in Section 3.
Table I
Non-compliance (Exceedance) Record for the Project in the Reporting Quarter
Parameter |
No. of Exceedance |
No. of Exceedance due to Construction Activities of this
Project |
Action Taken |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
||
May
2024 |
|||||
Air
Quality |
0 |
0 |
0 |
0 |
N/A |
Noise |
0 |
0 |
0 |
0 |
N/A |
Marine Water Quality |
N/A |
N/A |
N/A |
N/A |
N/A |
Groundwater Level Monitoring (Piezometer
Monitoring) |
N/A |
N/A |
N/A |
N/A |
N/A |
Ecological |
N/A |
N/A |
N/A |
N/A |
N/A |
Cultural Heritage |
N/A |
N/A |
N/A |
N/A |
N/A |
Landfill Gas |
N/A |
N/A |
N/A |
0 |
N/A |
June
2024 |
|||||
Air
Quality |
0 |
0 |
0 |
0 |
N/A |
Noise |
0 |
0 |
0 |
0 |
N/A |
Marine Water Quality |
N/A |
N/A |
N/A |
N/A |
N/A |
Groundwater Level Monitoring (Piezometer
Monitoring) |
N/A |
N/A |
N/A |
N/A |
N/A |
Ecological |
N/A |
N/A |
N/A |
N/A |
N/A |
Cultural Heritage |
N/A |
N/A |
N/A |
N/A |
N/A |
Landfill Gas |
N/A |
N/A |
N/A |
0 |
N/A |
July
2024 |
|||||
Air
Quality |
0 |
0 |
0 |
0 |
N/A |
Noise |
0 |
0 |
0 |
0 |
N/A |
Marine Water Quality |
N/A |
N/A |
N/A |
N/A |
N/A |
Groundwater Level Monitoring (Piezometer
Monitoring) |
N/A |
N/A |
N/A |
N/A |
N/A |
Ecological |
N/A |
N/A |
N/A |
N/A |
N/A |
Cultural Heritage |
N/A |
N/A |
N/A |
N/A |
N/A |
Landfill Gas |
N/A |
N/A |
N/A |
0 |
N/A |
Note: N/A - Not Applicable. |
6.
Summary of key information in the reporting quarter is tabulated in Table II.
Table
II
Summary Table for Key Information in the Reporting Quarter
Event |
Event Details |
Action Taken |
Status |
|
Number |
Nature |
|||
Complaints Received |
0 |
--- |
N/A |
N/A |
Notifications of any summons & prosecutions received |
0 |
--- |
N/A |
N/A |
N/A – Not Applicable |
7. Environmental
monitoring works for the Project are considered effective and is generating
data to categorically identify the environmental impacts from the works and influencing factors in the vicinity of monitoring stations.
8. No reporting change in the reporting quarter.
1.1
In 2009,
Civil Engineering and Development Department (CEDD) commissioned a Kai Tak
Development (KTD) – Trunk Road T2 and Infrastructure at South Apron
Investigation. The assignment covers the provision of the Trunk Road T2 and its
connections with the Central Kowloon Route (CKR) at the north apron area and
the Tseung Kwan O – Lam Tin Tunnel (TKOLTT) to the south in the Cha Kwo Ling
area.
1.2
The Trunk Road T2 Project is one of the designated Projects under
Schedule 2 of the EIAO proposed in the KTD. CEDD submitted the Project Profile
(No. PP-379/2009) on 24 March 2009 for application for an EIA study brief for
the Trunk Road T2 Project under the EIAO. Accordingly, an EIA Study Brief
(ESB-203/2009) for the Trunk Road T2 Project was issued on 30 April 2009. The
Environmental Impact Assessment (EIA) Report for the Trunk Road T2 Project was
approved under the Environmental Impact Assessment Ordinance (EIAO) on 19
September 2013. The corresponding Environmental Permit (EP) was issued on 19
September 2013 (EP no.: EP-451/2013).
1.3
The Contract No. ED/2018/04 is the main contract of Trunk Road T2 (“T2
Main Works”) which comprises mainly the design and construction of a dual
two-lane trunk road of approximately 3.0km long with about 2.7km of the trunk
road in form of tunnel; ventilation and administration buildings, environmental
protection and mitigation works and etc. The EM&A programme under this
Contract is governed by the two EPs (EP-451/2013 and EP-458/2013/C) and two
EM&A Manuals (AEIAR-174/2013 and AEIAR-173/2013). The work areas of the T2
Main Works are shown in Figure 1 and
the works to be executed under this Contract and corresponding EPs are
summarized as follows:
Environmental
Permit |
Works Description |
EP-451/2013 – Trunk Road T2 |
Trunk Road T2 · Construction of highway
and sub-sea tunnel connecting between Central Kowloon Route and Cha Kwo Ling
Tunnel · Western & Eastern
Ventilation Buildings |
EP-458/2013/C – Tseung Kwan O – Lam Tin Tunnel (TKOLTT) and Associated
Works |
Cha Kwo Ling Tunnel Construction of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to
the TKOLTT at the Eastern Ventilation Building |
Monitoring Works in Lam Tin under EP-458/2013/C
1.4
Under
Agreement No. CE 59/2015 (EP) – Tseung Kwan O – Lam Tin Tunnel (TKOLLT) and
Associated Works, the baseline monitoring works in Lam Tin under the EM&A
Manual (AEIAR-173/2013) were conducted by the Environmental Team (ET) for the
Agreement No. CE 59/2015 (EP) at the approved monitoring locations, namely AM1,
AM2, AM3, AM4, AM4 (A) CM1, CM2, CM3, CM4 and CM5. Impact monitoring within the
Lam Tin area shall be conducted by the ET of Contract No. ED/2018/04 upon
cessation of Agreement No. CE 59/2015 (EP). The data obtained from the impact
monitoring works completed by the ET of Agreement No. CE 59/2015 (EP) will be
adopted in this report
1.5
Cinotech Consultants Ltd. was designated as the Environmental Team (ET) to undertake the EM&A works for “Trunk Road T2 and Infrastructure Works for
Developments at the Former South Apron” (hereinafter called the
“Project”).
1.6
This is the
17th Quarterly EM&A Summary Report summarizing the EM&A
works for the Project in between May 2024 and July 2024.
1.7
Different
parties with different levels of involvement in the project organization
include:
·
Permit
Holder – Civil Engineering and Development Department (CEDD)
·
Supervisor
Representative – Hyder-Meinhardt Joint Venture (HMJV)
·
Environmental
Team (ET) – Cinotech Consultants Limited (Cinotech)
·
Independent
Environmental Checker (IEC) – Ramboll Hong Kong Limited (Ramboll)
·
Contractor
– Bouygues Travaux Publics (BTP)
1.8
The key
contacts of the Project are shown in Table
1.1.
Table
1.1 Key Project
Contacts
Party |
Role |
Contact
Person |
Phone No. |
CEDD |
Permit Holder |
Mr. Wong Chi Wai, Tommy |
3842 7111 |
HMJV |
Supervisor Representative |
Ms. Hazel Tang |
2149 8524 |
Cinotech |
Environmental Team |
Mr. KS Lee (ETL) |
2151 2091 |
Ms. Karina Chan |
2157 3880 |
||
Ramboll |
Independent Environmental Checker |
Mr. YH Hui |
3465 2850 |
BTP |
Contractor |
Mr. Roy Leung |
6628 2685 |
1.9
The
Organizational Structure for Environmental Management is shown in Figure 1.2.
1.10
The major site activities undertaken in the reporting quarter are shown as follow:
Contract
No. |
Project
Title |
Reporting
month |
Site
Activities |
ED/2018/04 |
Trunk Road T2 and Infrastructure Works for
Developments at South Apron |
May
2024 |
1.
East Bound – Wall & Crown 2.
East Ventilation Building – RC Structure, ABWF, E&M 3.
West Bound – Bulkhead Construction, OHVD |
June
2024 |
1. East Ventilation Building RC Structure 2. East Ventilation Building ABWF 3. East Ventilation Building E&M 4. East Bound –
Wall & Crown 5. West Bound – OHVD 6. West Bound – Bulkhead Construction |
||
July
2024 |
1. East Ventilation Building RC Structure 2. East Ventilation Building ABWF 3. East Ventilation Building E&M 4. East Bound – Wall & Crown 5. West Bound – OHVD 6. West Bound – Bulkhead Construction |
||
ED/2020/03 |
Trunk Road T2 - Traffic Control And Surveillance
System (TCSS) and Associated Works(1) |
May
2024 – July
2024 |
N/A |
(1):
No major construction work was undertaken during reporting quarter.
2.1
The EM&A Manual designates locations for environmental monitoring in
terms of air quality, noise, and landfill gas due to the Project. The Project
area and monitoring locations are depicted in Figures 2. Appendix A
gives details of monitoring requirements.
2.2
Monitoring works/equipment were conducted/calibrated regularly in
accordance with the EM&A Manual. Copies of calibration certificates are
attached in the appendices of the corresponding Monthly EM&A Reports.
2.3
The environmental quality performance limits, i.e. Action and Limit
Levels were derived from the baseline monitoring results. Should the measured
environmental quality parameters exceed the Action/Limit Levels, the respective
action plans would be implemented. The
Action/Limit Levels for each environmental parameter are given in Appendix B.
2.4
Should the
monitoring results of the environmental monitoring parameters at any designated
monitoring stations indicate that the Action / Limit Levels are exceeded, the
actions in accordance with the Event and Action Plans in Appendix K was carried out.
2.5
Relevant mitigation measures as recommended in the project EIA report
have been stipulated in the EM&A Manual for implementation by the
Contractor. The implementation status of environmental
mitigation measures (EMIS) is given in Appendix
G.
2.6
During site inspections in the reporting period, no non-compliances was recorded.
The observations and recommendations made during the reporting period are
summarized in Appendix F.
2.7
The amount of wastes generated by the construction activities during the
reporting period is shown in Appendix H.
3.1
The weather
during monitoring sessions was summarized in Table 3.1.
Table 3.1 Summary
of Weather Conditions in the
Reporting Period
Reporting Month |
General Weather Conditions |
May 2024 |
Sunny, Cloudy, Fine |
June 2024 |
Sunny, Cloudy, Fine |
July 2024 |
Sunny, Cloudy, Fine |
3.2
The detail of weather conditions for
each individual monitoring session was presented in the corresponding monthly
EM&A report.
3.3
All 1-hour TSP monitoring was conducted as scheduled in the
reporting quarter. No Action/Limit Level exceedance was recorded.
3.4
All 24-hour TSP monitoring was conducted as
scheduled in the reporting quarter No Action/Limit Level exceedance
was recorded in the reporting quarter.
3.5
The graphical presentations of the air quality monitoring results
are shown in Appendix C.
3.6
All noise monitoring was conducted as scheduled in the reporting
month. No Action Level exceedance was recorded in this reporting quarter and no
Limit Level exceedance was recorded in this
reporting quarter. The graphical
presentations of the noise monitoring results are shown in Appendix D.
Groundwater Quality
3.7
The
existing groundwater quality monitoring programme has been suspended as the
monitoring results had been deemed non-representative of the impact from the
project justified by two major factors: (1) influence on the monitoring results
from non-project related factors, such as anthropogenic activities and natural
phenomenon; and (2) large separation between the monitoring stations and works
area. In addition, as no alternative locations for the groundwater quality
monitoring were available, the groundwater quality monitoring has been
suspended since October 2019 upon the agreement by EPD
Marine Water Quality
3.8
According
to Section 4.4.3 of EM&A Manual (AEIAR-173/2013), marine water quality impact
monitoring stations is carried out during marine construction for TKOLTT
reclamation. Since the construction of Cha Kwo Ling Tunnel from the end of
Trunk Road T2 to the TKOLTT at the Eastern Ventilation Building does not
involve reclamation, the marine water quality monitoring programme stated in
Section 4.4 of the EM&A Manual (AEIAR-173/2013) is therefore not applicable to Contract
No. ED/2018/04.
Groundwater Level Monitoring (Piezometer Monitoring)
3.9
According
to Section 4.1.2 of EM&A Manual (AEIAR-173/2013), daily piezometer monitoring will be
carried out on a daily basis when any tunnel construction activities are
carried out within +/- 50m of the piezometer gate in plan. As the construction
works of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to the TKOLTT at the
Eastern Ventilation Building is approximately 120m away from
the piezometer gate in plan, the
piezometer monitoring programme stated in Section 4.2 of the EM&A
Manual (AEIAR-173/2013) is
therefore not applicable to Contract No. ED/2018/04
3.10
Post-translocation monitoring survey is recommended
in Section 6.2.5 of the EM&A Manual (AEIAR-173/2013), to audit the success
of coral translocation. Since the construction of Cha Kwo Ling Tunnel from the
end of Trunk Road T2 to the TKOLTT at the Eastern Ventilation Building does not
involve any marine works in the concerned area mentioned in Section 6.1.2 of
the EM&A Manual (AEIAR-173/2013), the post-translocation monitoring survey
stated in Section 6.2.5 of the EM&A Manual (AEIAR-173/2013) is therefore not
applicable to Contract No. ED/2018/04.
3.11
As the construction works of Cha Kwo Ling Tunnel from the end of Trunk
Road T2 to the TKOLTT at the Eastern Ventilation Building are located more than
100m away from the Cha Kwo Ling Tin Hau temple, the vibration impact monitoring
stated in Section 8.3.1 of the EM&A Manual (AEIAR-173/2013) is not
applicable to Contract No. ED/2018/04.
3.12
The implementation of landscape and visual mitigation measures was
checked during the environmental site inspections. Recommended follow-up
actions have been discharged by the Contractor. Details of the audit findings
and implementation status are presented in Appendix
F.
3.13
Since no excavation activity for this Project was carried out within the
Sai Tso Wan Landfill Consultation Zone in this reporting quarter, therefore, no
landfill gas monitoring was required.
3.14
Site audits were carried out on a weekly basis to monitor and ensures that
proper storage, transportation and disposal practices of wastes generated from
this Project include inert construction and demolition (C&D) materials,
non-inert C&D materials. Details of waste management data is presented in Appendix H.
3.15
According to Section 7.1.3 of EM&A Manual (AEIAR-173/2013), no
specific fisheries monitoring programme is required during the construction
phase.
3.16
During the reporting period, the major dust and noise source
identified at the designated monitoring stations are as follows:
Table
3.2 Major
Dust Sources during the Monitoring in the Reporting Period
Station |
Major Dust Source |
AM1 – Tin Hau Temple |
Road Traffic at Cha
Kwo Ling Road |
AM2 – Sai Tso Wan
Recreation Ground |
Road Traffic along Sin
Fat Road |
AM3 – Yau Lai Estate
Bik Lai House |
Road Traffic near
Eastern Cross Harbour Tunnel Toll Plaza |
AM4 - Sitting-out Area
at Cha Kwo Ling Village |
Road Traffic at Cha
Kwo Ling Road |
AM4(B) - Cha Kwo Ling
Public Cargo Working Area Administrative Office * |
Road Traffic at Cha
Kwo Ling Road |
*:
AM4(A) is not available for conducing monitoring due to the demolition of
administrative office, the relocation of monitoring station from AM4(A) to
AM4(B) has been approved by EPD on 11 July 2022.
Table
3.3 Major
Noise Sources during the Monitoring in the Reporting
Period
Monitoring Stations |
Locations |
Major Noise Source |
CM1 |
Nga Lai House, Yau Lai Estate
Phase 1, Yau Tong |
Road Traffic near Eastern
Cross Harbour Tunnel Toll Plaza |
CM2 |
Bik Lai House, Yau Lai Estate
Phase 1, Yau Tong |
Road
Traffic near Eastern Cross Harbour Tunnel Toll Plaza |
CM3 |
Block S, Yau Lai Estate Phase 5,
Yau Tong |
Road Traffic near Eastern
Cross Harbour Tunnel Toll Plaza |
CM4 |
Tin Hau Temple, Cha Kwo Ling |
Road Traffic at Cha Kwo Ling
Road |
CM5 |
CCC Kei Faat Primary School, Yau
Tong |
Road Traffic near Eastern
Cross Harbour Tunnel Toll Plaza |
4.1
Environmental
monitoring works were performed in the reporting period and all monitoring
results were checked and reviewed. A
summary of exceedances is attached in Appendix
I.
Air Quality
4.2
No Action Level exceedance was recorded in the
reporting quarter. No Limit Level exceedance was recorded in the reporting
quarter
Construction
Noise
4.3
No Action Level exceedance was recorded due to the documented complaint
in the reporting quarter.
4.4
No Limit Level exceedance for construction noise monitoring was recorded
in the reporting quarter.
Review of
the Reasons for and the Implications of Non-compliance
4.5
During site audits in the reporting quarter, no non-compliance was
recorded. Recommendations made in each individual site audit session were
attached in the Appendix F.
Landscape and Visual
4.6
No non-compliance of the landscape and visual impact was recorded in the
reporting quarter.
4.7
No environmental complaint on this Project was received in the reporting
quarter.
4.8
No environmental warning, prosecution and notification of summons were
received in the reporting quarter.
5.1
The EM&A methodology has been effective in monitoring the
environmental impacts of the Project and the effectiveness of the mitigation
measures. The data collected were useful in determining whether the Project had
caused unacceptable impacts on the sensitive receivers. Analysis of all
EM&A data collected throughout the baseline and the impact periods
demonstrated the environmental acceptability of the Project
5.2
The mitigation measures recommended in the EIA report are
considered effective in minimizing environmental impacts.
5.3
The Contractor has implemented the recommended mitigation measures
except those mitigation measures not applicable at this stage.
5.4
Environmental monitoring works were performed in the reporting
quarter and all monitoring results were checked and reviewed.
5.5
The summary record of non-compliance (exceedances) of Action/Limit
Level for environmental monitoring in the reporting quarter has been presented
in Table I above and in Appendix I.
5.6
No environmental complaint was received in the reporting quarter. The details were attached in the Appendix J.
5.7
No warning, notification of summon and environmental prosecution
was received in the reporting quarter. The details were attached in the Appendix
J.
5.8
Joint weekly site audits by the representatives of the Engineer,
Contractor and the ET were conducted in the reporting quarter. The following
recommendations was made to the Contractor for the coming reporting month:
Air quality:
·
3-sides barriers should be provided when conducting the cement mixing.
·
Water spraying should be applied on the unpaved area.
·
The valid NRMM label should be displayed on the PMEs.
Noise:
·
The noise barriers should be erected properly in the construction site.
Water quality:
·
The stagnant water should be removed regularly and avoid water ponding.
Waste /
Chemical Management
·
The drip tray should be provided for the chemical container to avoid the
chemical leakage.
·
The machinery should be checked and maintenance regularly to prevent the
oil leakage.
·
The site and surrounding should be kept tidy and litter free, remove the
waste regularly.