TABLE OF CONTENTS
Summary of Main Works Undertaken and Key Measures Implemented
Environmental
Monitoring Works
Summary
of Complaint, Warning, Notification of Summons and Successful Prosecution
Reporting Changes in the Reporting Quarter
Construction
Activities undertaken during the Report Quarter
2. ENVIRONMENTAL MONITORING AND AUDIT
REQUIREMENTS
Monitoring
Parameters and Monitoring Locations
Monitoring
Methodology and Calibration Details
Environmental
Quality Performance Limits (Action and Limit Levels)
Implementation Status of Environmental Mitigation Measures
Monitoring on Cultural Heritage
Landscape and Visual Monitoring and Audit
Influencing Factors on the Monitoring Results
Review of the Reasons for and the Implications of Non-compliance
Summary of Environmental Complaints and Prosecutions
5. COMMENTS, CONCLUSIONS AND RECOMMENDATIONS
Review of Monitoring Methodology and the Practicality and
Effectiveness of EM&A Programme
Effectiveness of Mitigation Measures
LIST OF TABLES
Table I Summary Table for
Non-compliance Recorded in the Reporting Quarter
Table II Summary Table for Key Information
in the Reporting Quarter
Table 1.1 Key Project Contacts
Table 3.1 Summary
of Weather Conditions in the Reporting Period
Table 3.2 Major
Dust Sources during the Monitoring in the Reporting Period
Table 3.3 Major
Noise Sources during the Monitoring in the Reporting Period
lIST OF FIGUREs
Figure 1 Site Layout Plan
Figure 1.2 Project Organisation for Environmental
Monitoring and Audit
Figure 2 Locations of Air Quality and
Construction Noise Monitoring Stations
LIST OF APPENDICES
C Graphical Presentation of Air Quality
Monitoring Results
D Graphical Presentation of Noise Monitoring
Results
E Graphical Presentation of Landfill Gas Monitoring
Results (Not used)
G Environmental Mitigation
Implementation Schedule (EMIS)
J Summaries of Environmental Complaint, Warning, Summon
and Notification of Successful Prosecution
1.
This
is the 25th
Quarterly Environmental Monitoring and Audit (EM&A) Report prepared by the
Environmental Team (ET), Cinotech Consultants Ltd., for Contract No. ED/2018/04
“Trunk Road T2 and Infrastructure Works for Developments at the Former South
Apron”, Contract No. ED/2020/03 “Trunk Road T2 - Traffic Control And
Surveillance System (TCSS) and Associated Works” and Contract No. NE/2015/01
“Tseung Kwan O – Lam Tin Tunnel–Main Tunnel and Associated Works”. This report
summarized the monitoring results and audits findings of the EM&A programme
under the issued Environmental Permit (EP) No. EP-458/2013/C and in accordance
with the EM&A Manual (AEIAR-173/2013) during the reporting period from May 2026 to July 2026.
2.
During
the reporting quarter, the following works contracts were undertaken within the
site:
·
Contract No.: ED/2018/04 -
Trunk Road T2 and Infrastructure Works for Developments at South Apron
·
Contract No.: ED/2020/03 - Trunk Road T2 - Traffic Control and
Surveillance System (TCSS) and Associated Works
·
Contract No.: NE/2015/01 - Tseung Kwan O – Lam Tin
Tunnel–Main Tunnel and Associated Works
3.
The construction activities undertaken in the reporting quarter
were as follows:
|
Contract No. |
Project Title |
Reporting Month |
Site Activities |
|
ED/2018/04 |
Trunk Road T2 and Infrastructure Works for Developments at South Apron |
May 2026 |
· CKL Tunnel Internal Structure · CKL – E&M works · EVB – E&M works · EVB – External works |
|
June 2026 |
· CKL Tunnel Internal Structure · CKL – E&M works · EVB – E&M works · EVB – External works |
||
|
July 2026 |
· CKL – E&M works · EVB – E&M works · EVB – External works |
||
|
ED/2020/03 |
Trunk Road T2 - Traffic
Control And Surveillance System (TCSS) and Associated Works |
May 2026 |
·
Installation of TCSS equipment, cable
containment and cable laying at CKL Tunnel, Branch Tunnel, TKO-LTI, EVB &
ADB |
|
June 2026 |
|||
|
July 2026 |
|||
|
NE/2015/01 |
Tseung Kwan O – Lam Tin Tunnel–Main Tunnel and Associated Works |
May 2026 |
· NA |
|
June 2026 |
|||
|
July 2026 |
4. Implementation of the key mitigation measures during the reporting period are as follows:
Construction Noise
· Construction activities were scheduled to minimize noise nuisance to the nearby sensitive receiver
· Conduct regular noise monitoring
· Use of Quality Powered Mechanical Equipment (QPME) on site
· Erected the noise barrier on site
· Close the site entry to reduce noise impact
Air Quality
· Regularly watering on site to avoid dust generation
· Cover cement bags with more than 20 bags per stack
Water Quality
· Pump out ponding water
Waste Management
· Avoid accumulation of general refuse or construction waste
Landscape and Visual
· Tree protection zones were fenced off to protect the existing trees on site
5. Environmental monitoring for the Project was performed in accordance with the EM&A Manual and the monitoring results were checked and reviewed. Site Inspections/Audits were conducted once per week. The implementation of the environmental mitigation measures, Event Action Plans and environmental complaint handling procedures were also checked.
6. Summary of the non-compliance in the reporting quarter for the Project is tabulated in Table I. Details of the environmental monitoring results is presented in Section 3.
Table I Non-compliance
(Exceedance) Record for the Project in the Reporting Quarter
|
Parameter |
No.
of Exceedance |
No.
of Exceedance due to Construction Activities of this Project |
Action
Taken |
||
|
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||
|
May 2026 |
|||||
|
Air Quality |
0 |
0 |
0 |
0 |
N/A |
|
Noise |
0 |
0 |
0 |
0 |
N/A |
|
Marine Water Quality |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Groundwater Level Monitoring (Piezometer Monitoring) |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Ecological |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Cultural Heritage |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Landfill Gas |
N/A |
N/A |
N/A |
0 |
N/A |
|
June 2026 |
|||||
|
Air Quality |
0 |
0 |
0 |
0 |
N/A |
|
Noise |
0 |
0 |
0 |
0 |
N/A |
|
Marine Water Quality |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Groundwater Level Monitoring (Piezometer Monitoring) |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Ecological |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Cultural Heritage |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Landfill Gas |
N/A |
N/A |
N/A |
0 |
N/A |
|
July 2026 |
|||||
|
Air Quality |
0 |
0 |
0 |
0 |
N/A |
|
Noise |
0 |
0 |
0 |
0 |
N/A |
|
Marine Water Quality |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Groundwater Level Monitoring (Piezometer Monitoring) |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Ecological |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Cultural Heritage |
N/A |
N/A |
N/A |
N/A |
N/A |
|
Landfill Gas |
N/A |
N/A |
N/A |
0 |
N/A |
|
Note: N/A - Not Applicable. |
|||||
7.
Summary of key information in the
reporting quarter is tabulated in Table
II.
Table II Summary
Table for Key Information in the Reporting Quarter
|
Event |
Event
Details |
Action
Taken |
Status |
|
|
Number |
Nature |
|||
|
Complaints
Received |
0 |
--- |
N/A |
N/A |
|
Notifications
of any summons & prosecutions received |
0 |
--- |
N/A |
N/A |
|
N/A
– Not Applicable |
||||
8. Environmental monitoring works for the Project are considered effective and is generating data to categorically identify the environmental impacts from the works and influencing factors in the vicinity of monitoring stations.
9. No reporting change in the reporting quarter.
1.1 In 2009, Civil Engineering and Development Department (CEDD) commissioned a Kai Tak Development (KTD) – Trunk Road T2 and Infrastructure at South Apron Investigation. The assignment covers the provision of the Trunk Road T2 and its connections with the Central Kowloon Route (CKR) at the north apron area and the Tseung Kwan O – Lam Tin Tunnel (TKOLTT) to the south in the Cha Kwo Ling area.
1.2 The Trunk Road T2 Project is one
of the designated Projects under Schedule 2 of the EIAO proposed in the KTD.
CEDD submitted the Project Profile (No. PP-379/2009) on 24 March 2009 for
application for an EIA study brief for the Trunk Road T2 Project under the
EIAO. Accordingly, an EIA Study Brief (ESB-203/2009) for the Trunk Road T2
Project was issued on 30 April 2009. The Environmental Impact Assessment (EIA)
Report for the Trunk Road T2 Project was approved under the Environmental
Impact Assessment Ordinance (EIAO) on 19 September 2013. The corresponding
Environmental Permit (EP) was issued on 19 September 2013 (EP no.:
EP-451/2013).
1.3 The Contract No. ED/2018/04 is the main contract
of Trunk Road T2 (“T2 Main Works”) which comprises mainly the design and
construction of a dual two-lane trunk road of approximately 3.0km long with
about 2.7km of the trunk road in form of tunnel; ventilation and administration
buildings, environmental protection and mitigation works and etc. Moreover, the
Contract No. ED/2020/03 is the other contract under Truck Road T2 Project which
comprises mainly design and construction of the TCSS for this Project. The
EM&A programme under the Contract ED/2018/04 and ED/2020/03 are governed by the two EPs
(EP-451/2013 and EP-458/2013/C) and two EM&A Manuals (AEIAR-174/2013 and
AEIAR-173/2013). The work areas of the T2 Main Works are shown in Figure 1 and the works to be executed
under these Contract and corresponding EPs are
summarized as follows:
|
Environmental Permit |
Works Description |
|
EP-451/2013 – Trunk Road T2 |
ED/2018/04 · Construction of highway and sub-sea tunnel
connecting between Central Kowloon Route and Cha Kwo Ling Tunnel · Western & Eastern Ventilation Buildings ED/2020/03 · Design and construction of TCSS for Trunk
Road T2 |
|
EP-458/2013/C – Tseung Kwan O – Lam Tin Tunnel (TKOLTT) and Associated
Works |
ED/2018/04 · Construction of Cha Kwo Ling Tunnel from the
end of Trunk Road T2 to the TKOLTT at the Eastern Ventilation Building ED/2020/03 · Design and construction of TCSS for Trunk
Road T2 |
Monitoring Works in Lam
Tin under EP-458/2013/C
1.4 Under Agreement No. CE 59/2015 (EP) – Tseung Kwan O – Lam Tin Tunnel (TKOLLT) and Associated
Works, the baseline monitoring works in Lam Tin under the EM&A Manual
(AEIAR-173/2013) were conducted by the Environmental Team (ET) for the
Agreement No. CE 59/2015 (EP) at the approved monitoring locations, namely AM1,
AM2, AM3, AM4, AM4 (A) CM1, CM2, CM3, CM4 and CM5. Impact monitoring within the
Lam Tin area shall be conducted by the ET of Contract No. ED/2018/04 upon
cessation of Agreement No. CE 59/2015 (EP). The data obtained from the impact
monitoring works completed by the ET of Agreement No. CE 59/2015 (EP) will be
adopted in this report
1.5 Cinotech Consultants Ltd. was designated as the
Environmental Team (ET) to undertake the EM&A works for “Trunk Road T2 and Infrastructure Works for Developments at the Former
South Apron” (hereinafter called the “Project”).
1.6 For the project “Tseung Kwan O – Lam Tin Tunnel and Associated Works” (TKO-LTT)
under EP-458/2013/C, all works contracts except Contract No. NE/2015/01 has
been terminated on 17 July 2025 after the approval by EPD. As Contract No.
NE/2015/01 (under TKO-LTT) and Contract No. ED/2018/04 & ED/2020/03 (under
Trunk Road T2) falls under the same EP 458/2013/C, the reporting of the
remaining EM&A works for Contract No. NE/2015/01 (Lam Tin portion of
TKO-LTT) will be subsumed into the EM&A reporting for the T2 project and
presented as a single combined report starting from August 2025.
1.7 This is the
25th Quarterly EM&A Summary Report summarizing the EM&A works
for the Project in between May 2026 to July 2026.
1.8 Different parties with different
levels of involvement in the project organization include:
· Permit Holder – Civil Engineering and Development Department (CEDD)
· Supervisor Representative – Hyder-Meinhardt Joint Venture (HMJV)
· Environmental Team (ET) – Cinotech Consultants Limited (Cinotech)
· Independent Environmental Checker (IEC) – Ramboll Hong Kong Limited (Ramboll)
· Contractor – Bouygues Travaux Publics (BTP)
1.9 The key contacts of the Project are shown in Table 1-1.
Table 1-1 Key Project Contacts
|
Party |
Role |
Contact Person |
Phone
No. |
|
CEDD |
Permit
Holder |
Mr.
NG Chou Keen, Horace |
3842
7091 |
|
HMJV |
Supervisor
Representative |
Ms.
Hazel Tang |
2149
8524 |
|
Cinotech |
Environmental
Team |
Mr.
KS Lee (ETL) |
2151
2091 |
|
Ms.
Karina Chan |
2157
3880 |
||
|
Ramboll |
Independent
Environmental Checker |
Mr.
YH Hui |
3465
2850 |
|
BTP |
Contractor
(ED/2018/04) |
Mr.
Mandy Cheung |
6604 6567 |
|
GTECH |
Contractor
(ED/2020/03) |
Mr.
Deacon Choi |
6038 3568 |
|
LCSJV |
Contractor
(NE/2015/01) |
Mr.
Valentine Ho |
3973 0409 |
1.10
The Organizational Structure for Environmental
Management is shown in Figure 1.2.
1.11 The major site activities undertaken in the reporting quarter are shown as follow:
|
Project Title |
Reporting Month |
Site Activities |
|
|
ED/2018/04 |
Trunk Road T2 and Infrastructure Works for Developments at South Apron |
May 2026 |
· CKL Tunnel Internal Structure · CKL – E&M works · EVB – E&M works · EVB – External works |
|
June 2026 |
· CKL Tunnel Internal Structure · CKL – E&M works · EVB – E&M works · EVB – External works |
||
|
July 2026 |
· CKL – E&M works · EVB – E&M works · EVB – External works |
||
|
ED/2020/03 |
Trunk Road T2 - Traffic
Control And Surveillance System (TCSS) and Associated Works |
May 2026 |
·
Installation of TCSS equipment, cable
containment and cable laying at CKL Tunnel, Branch Tunnel, TKO-LTI, EVB &
ADB |
|
June 2026 |
|||
|
July 2026 |
|||
|
NE/2015/01 |
Tseung Kwan O – Lam Tin Tunnel–Main Tunnel and Associated Works |
May 2026 |
· NA |
|
June 2026 |
|||
|
July 2026 |
2.1
The EM&A Manual designates locations for environmental monitoring in
terms of air quality, noise, and landfill gas due to the Project. The Project
area and monitoring locations are depicted in Figures 2. Appendix A
gives details of monitoring requirements.
2.2
Monitoring works/equipment were conducted/calibrated regularly in
accordance with the EM&A Manual. Copies of calibration certificates are
attached in the appendices of the corresponding Monthly EM&A Reports.
2.3
The environmental quality performance limits, i.e. Action and Limit
Levels were derived from the baseline monitoring results. Should the measured
environmental quality parameters exceed the Action/Limit Levels, the respective
action plans would be implemented. The
Action/Limit Levels for each environmental parameter are given in Appendix B.
2.4
Should the monitoring
results of the environmental monitoring parameters at any designated monitoring
stations indicate that the Action / Limit Levels are exceeded, the actions in
accordance with the Event and Action Plans in Appendix K was carried out.
2.5
Relevant mitigation measures as recommended in the project EIA report
have been stipulated in the EM&A Manual for implementation by the
Contractor. The implementation status of environmental
mitigation measures (EMIS) is given in Appendix
G.
2.6
During site inspections in the reporting period, no non-compliances was
recorded. The observations and recommendations made during the reporting period
are summarized in Appendix F.
2.7
The amount of wastes generated by the construction activities during the
reporting period is shown in Appendix H.
3.1 The weather during monitoring sessions was summarized in Table 3-1.
Table 3-1 Summary of Weather Conditions in the
Reporting Period
|
Reporting Month |
General Weather Conditions |
|
May
2026 |
Sunny, Cloudy, Fine, Rainy |
|
June
2026 |
Sunny, Cloudy, Fine, Rainy |
|
July
2026 |
Sunny, Cloudy, Fine, Rainy |
3.2
The
detail of weather conditions for each
individual monitoring session was presented in the corresponding monthly
EM&A report.
3.3
All
1-hour TSP monitoring was conducted as scheduled in the reporting quarter. No
Action/Limit Level exceedance was recorded.
3.4
All 24-hour TSP monitoring was conducted as
scheduled in the reporting quarter No Action/Limit Level exceedance was
recorded in the reporting quarter.
3.5
The
graphical presentations of the air quality monitoring results are shown in Appendix C.
3.6
All
noise monitoring was conducted as scheduled in the reporting month. No Action Level exceedance was
recorded in this reporting quarter, and no Limit Level exceedance was recorded in this reporting
quarter. The graphical presentations of the noise
monitoring results are shown in Appendix
D.
Groundwater Quality
3.7
The existing groundwater quality monitoring programme has been
suspended as the monitoring results had been deemed non-representative of the
impact from the project justified by two major factors: (1) influence on the
monitoring results from non-project related factors, such as anthropogenic
activities and natural phenomenon; and (2) large separation between the
monitoring stations and works area. In addition, as no alternative locations
for the groundwater quality monitoring were available, the groundwater quality
monitoring has been suspended since October 2019 upon the agreement by EPD.
Marine
Water Quality
3.8 According to Section 4.4.3 of EM&A Manual (AEIAR-173/2013), marine water quality impact monitoring stations is carried out during marine construction for TKOLTT reclamation. Since the construction of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to the TKOLTT at the Eastern Ventilation Building does not involve reclamation, the marine water quality monitoring programme stated in Section 4.4 of the EM&A Manual (AEIAR-173/2013) is therefore not applicable to Contract No. ED/2018/04.
Groundwater Level Monitoring (Piezometer
Monitoring)
3.9
According to Section 4.1.2 of EM&A Manual (AEIAR-173/2013), daily piezometer monitoring will be carried out on
a daily basis when any tunnel construction activities are carried out within
+/- 50m of the piezometer gate in plan. As the construction works of Cha Kwo
Ling Tunnel from the end of Trunk Road T2 to the TKOLTT at the Eastern
Ventilation Building is approximately 120m away from the piezometer gate in plan, the piezometer monitoring programme stated in Section 4.2
of the EM&A Manual (AEIAR-173/2013) is
therefore not applicable to Contract No. ED/2018/04
3.10
Post-translocation monitoring survey
is recommended in Section 6.2.5 of the EM&A Manual (AEIAR-173/2013), to
audit the success of coral translocation. Since the construction of Cha Kwo
Ling Tunnel from the end of Trunk Road T2 to the TKOLTT at the Eastern
Ventilation Building does not involve any marine works in the concerned area
mentioned in Section 6.1.2 of the EM&A Manual (AEIAR-173/2013), the
post-translocation monitoring survey stated in Section 6.2.5 of the EM&A
Manual (AEIAR-173/2013) is therefore not applicable to Contract No. ED/2018/04.
3.11
As
the construction works of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to
the TKOLTT at the Eastern Ventilation Building are
located more than 100m away from the Cha Kwo Ling Tin Hau temple, the vibration
impact monitoring stated in Section 8.3.1 of the EM&A Manual (AEIAR-173/2013) is not applicable
to Contract No. ED/2018/04.
3.12
The implementation of landscape and
visual mitigation measures was checked during the environmental site
inspections. Recommended follow-up actions have been discharged by the
Contractor. Details of the audit findings and implementation status are
presented in Appendix F.
3.13
Since no excavation activity for this Project was carried out within the
Sai Tso Wan Landfill Consultation Zone in this reporting quarter, therefore, no
landfill gas monitoring was required.
3.14
Site audits were carried out on a weekly basis to monitor and ensures
that proper storage, transportation and disposal practices of wastes generated
from this Project include inert construction and demolition (C&D)
materials, non-inert C&D materials. Details of waste management data is
presented in Appendix H.
3.15
According to Section 7.1.3 of EM&A Manual (AEIAR-173/2013), no
specific fisheries monitoring programme is required during the construction
phase.
3.16
During
the reporting period, the major dust and noise source identified at the
designated monitoring stations are as follows:
Table 3-2 Major Dust Sources during the Monitoring in
the Reporting Period
|
Station |
Major Dust Source |
|
AM1 – Tin Hau Temple |
Road Traffic at Cha Kwo Ling Road |
|
AM2 – Sai Tso Wan Recreation
Ground |
Road Traffic along Sin Fat Road |
|
AM3 – Yau Lai Estate Bik Lai House |
Road Traffic near Eastern Cross
Harbour Tunnel Toll Plaza |
|
AM4 - Sitting-out Area at Cha Kwo
Ling Village |
Road Traffic at Cha Kwo Ling Road |
|
AM4(B) - Cha Kwo Ling Public Cargo
Working Area Administrative Office * |
Road Traffic at Cha Kwo Ling Road |
*: AM4(A) is not available for conducing monitoring
due to the demolition of administrative office, the relocation of monitoring
station from AM4(A) to AM4(B) has been approved by EPD on 11 July 2022.
Table 3-3 Major
Noise Sources during the Monitoring in the Reporting Period
|
Monitoring Stations |
Locations |
Major Noise Source |
|
CM1 |
Nga Lai House, Yau
Lai Estate Phase 1, Yau Tong |
Road Traffic near Eastern Cross Harbour
Tunnel Toll Plaza |
|
CM2 |
Bik Lai House, Yau
Lai Estate Phase 1, Yau Tong |
Road Traffic near
Eastern Cross Harbour Tunnel Toll Plaza |
|
CM3 |
Block S, Yau Lai
Estate Phase 5, Yau Tong |
Road Traffic near Eastern Cross Harbour
Tunnel Toll Plaza |
|
CM4 |
Tin Hau Temple, Cha
Kwo Ling |
Road Traffic at Cha Kwo Ling Road |
|
CM5 |
CCC Kei Faat Primary
School, Yau Tong |
Road Traffic near Eastern Cross Harbour
Tunnel Toll Plaza |
4.1 Environmental monitoring works were performed in the reporting period and all monitoring results were checked and reviewed. A summary of exceedances is attached in Appendix I.
Air Quality
4.2
No Action
Level exceedance was recorded in the reporting quarter. No Limit Level
exceedance was recorded in the reporting quarter.
Construction Noise
4.3
No Action Level exceedance was
recorded due to the documented complaint in the reporting quarter.
4.4
No Limit Level exceedance for construction noise monitoring was recorded
in the reporting quarter.
Landscape
and Visual
4.6
No non-compliance of the landscape and visual impact was recorded in the
reporting quarter.
4.7
No environmental complaint on this Project was received in the reporting
quarter.
4.8
No environmental warning, prosecution and notification of summons were
received in the reporting quarter.
5.1 The EM&A methodology has been effective in monitoring the environmental impacts of the Project and the effectiveness of the mitigation measures. The data collected were useful in determining whether the Project had caused unacceptable impacts on the sensitive receivers. Analysis of all EM&A data collected throughout the baseline and the impact periods demonstrated the environmental acceptability of the Project.
5.2
The
mitigation measures recommended in the EIA report are considered effective in
minimizing environmental impacts.
5.3
The
Contractor has implemented the recommended mitigation measures except those
mitigation measures not applicable at this stage.
5.4
Environmental
monitoring works were performed in the reporting quarter and all monitoring
results were checked and reviewed.
5.5
The
summary record of non-compliance (exceedances) of Action/Limit Level for
environmental monitoring in the reporting quarter has been presented in Table
I above and in Appendix I.
5.6
No environmental complaint was received in the reporting quarter. The details
were attached in the Appendix J.
5.7
No
warning, notification of summon and environmental prosecution was received in
the reporting quarter. The details were attached in the Appendix J.
5.8
Joint
weekly site audits by the representatives of the Engineer, Contractor and the
ET were conducted in the reporting quarter. The following recommendations was
made to the Contractor for the coming reporting month:
Water Quality
·
Ponding water should be avoided
Air Quality
·
NRMM Label should be provided to PME
·
Cement bags should be covered with a top if more than 20 bags per stack
Waste / Chemical
Management
·
The construction waste / general refuse should be removed and disposed
timely