Table of contents

Page

1.       EXECUTIVE SUMMARY.. 1

Introduction. 1

Summary of Main Works Undertaken and Key Measures Implemented. 1

Environmental Monitoring Works. 1

Key Information in the Reporting Month. 4

Reporting Changes. 5

Future Key Issues. 5

1.       INTRODUCTION.. 6

Background. 6

Purpose of the Report 7

Project Organizations. 7

Construction Activities undertaken during the Reporting Month. 7

Summary of EM&A Requirements. 8

Status of Environmental Licensing and Permitting. 8

2.       NOISE.. 9

Maintenance and Calibration. 10

3.       WATER QUALITY.. 13

4.       WASTE MANGEMENT.. 13

5.       ECOLOGY.. 14

6.       FISHERIES. 14

7.       CULTURAL HERITAGE.. 14

8.       LANDSCAOPE AND VISUAL IMPACT.. 15

9.       LANDFILL GAS MONITORING.. 15

Monitoring Requirement 15

10.    HAZARD TO LIFE.. 15

11.    ENVIRONEMNTAL AUDIT.. 16

Site Audits. 16

Implementation Status of Environmental Mitigation Measures. 16

Implementation Status of Event and Action Plans. 17

12.    ENVIRONMENTAL NON-COMFORMANCE.. 17

Summary of Complaint, Warning, Notification of any Summons and Successful Prosecution. 17

Summary of Exceedance. 17

13.    FUTURE KEY ISSUES. 17

Monitoring Schedule. 18

14.    CONCLUSION AND RECOMMENDATION.. 19

Conclusions. 19

Recommendations. 19

 

lIST OF TABLES

 

Table I            Non-compliance (exceedance) Record for the Project in the Reporting Month

Table II           Monthly Complaints, Notifications of Summons and Successful Prosecutions in the Reporting Month

Table III          Summary of Complaints Details in Reporting Month

Table IV          Summary Table for Site Activities in the next Reporting Period

Table 1.1         Key Project Contacts

Table 1.2         Summary of Environmental License and Permit

Table 2.1         Air Quality Monitoring Locations

Table 2.2         Frequency and Parameters of Air Quality Monitoring

Table 2.3         Air Quality Monitoring Equipment

Table 2.4         Major Dust Source during Air Quality Monitoring

Table 2.5         Comparison of 1-hr TSP Monitoring Data with Predictions in EIA Report

Table 2.6         Comparison of 24-hr TSP Monitoring Data with Predictions in EIA Report

Table 3.1         Noise Monitoring Stations

Table 3.2         Frequency and Parameters of Noise Monitoring

Table 3.3        Noise Monitoring Equipment

Table 3.4         Other Noise Source Identified during Noise Monitoring

Table 3.5         Baseline Noise Level and Noise Limit Level for Monitoring Stations

Table 3.6         Maximum Predicted Mitigated Construction Noise Levels in EIA Report

Table 10.1       Landfill Gas Monitoring Equipment (not used)

Table 12.1       Observations and Recommendations of Site Audit

 

 

 

 

 

lIST OF FIGUREs

 

Figure 1           Site Layout Plan

Figure 1.2        Organizational Structure for Environmental Management

Figure 2           Locations of Air Quality and Construction Noise Monitoring Stations

 

 

lIST OF APPENDIces

 

Appendix A    Action and Limit Levels

Appendix B    Copies of Calibration Certificates

Appendix C    Weather Information

Appendix D    Environmental Monitoring Schedules

Appendix E     1-hour TSP Monitoring Results and Graphical Presentations

Appendix F     24-hour TSP Monitoring Results and Graphical Presentations

Appendix G    Noise Monitoring Results and Graphical Presentations

Appendix H    Waste Generation in the Reporting Month

Appendix I      Site Audit Summary

Appendix J      Environmental Mitigation Implementation Schedule (EMIS)

Appendix K    Record of Landfill Gas Monitoring by Contractor (not used)

Appendix L     Event and Action Plans

Appendix M   Summaries of Environmental Complaint, Warning, Summon and Notification of Successful Prosecution

Appendix N    Summary of Exceedance

Appendix O    Tentative Construction Programme

                       

 

 

 


1.          EXECUTIVE SUMMARY

Introduction

 

1.             This is the 41st Environmental Monitoring and Audit (EM&A) Report prepared by the Environmental Team (ET), Cinotech Consultants Ltd., for Contract No. ED/2018/04 ˇ§Trunk Road T2 and Infrastructure Works for Developments at the Former South Apronˇ¨. This report summarized the monitoring results and audits findings of the EM&A programme under the issued Environmental Permit (EP) No. EP-458/2013/C and in accordance with the EM&A Manual (AEIAR-173/2013) during the reporting month of September 2023.

Summary of Main Works Undertaken and Key Measures Implemented

 

2.      The main works undertaken during the reporting period are as follows:

 

        East Bound ˇV RC Structure Construction, Lining

        East Ventilation Building ˇV RC Structure.

        West Bound ˇVRC Structure Construction, Pilot Tunnel Excavation, Lining

 

3.      Implementation of the key mitigation measures during the reporting period are as follows:

 

             Construction Noise

        Construction activities were scheduled to minimize noise nuisance to the nearby sensitive receiver.

        Use of Quality Powered Mechanical Equipment (QPME) on site.

        Erected the noise barrier on site.

            Air Quality

        Regularly watering on site to avoid dust generation.

            Landscape and Visual

        Tree protection zones were fenced off to protect the existing trees on site.

Environmental Monitoring Works

 

4.      Environmental monitoring for the Project was performed in accordance with the EM&A Manual and the monitoring results were checked and reviewed. Site Inspections/Audits were conducted once per week. The implementation of the environmental mitigation measures, Event Action Plans and environmental complaint handling procedures were also checked.

 

5.      Summary of the non-compliance (exceedance) in the reporting month for the Project is tabulated in Table I.

 

 

 

 

Table I       Non-compliance (exceedance) Record for the Project in the Reporting Month

Environmental Monitoring

No. of Non-compliance (Exceedance)

No. of Non-compliance (Exceedance)

due to Construction Activities of this Project

Action Taken

Action Level

Limit Level

Action Level

Limit Level

Air Quality

0

0

0

0

N/A

Noise

1

0

0

0

Refer to App M

Marine Water Quality

N/A

N/A

N/A

N/A

N/A

Groundwater Level Monitoring (Piezometer Monitoring)

N/A

N/A

N/A

N/A

N/A

Ecological

N/A

N/A

N/A

N/A

N/A

Cultural Heritage

N/A

N/A

N/A

N/A

N/A

Landfill Gas

N/A(1)

N/A

N/A(1)

N/A

N/A

Note: (1): No Action Level for Landfill Gas Monitoring.

 

Air Quality Monitoring

 

6.      No Action/Limit Level exceedance for 1-hour TSP monitoring was recorded.

 

7.      No Action Level exceedance and no Limit Level exceedance was recorded for 24-hour TSP monitoring in the reporting month.

 

Construction Noise Monitoring

 

8.      One (1) Action Level exceedance was recorded due to documented complaint in the reporting month. The Summary of Documented Complaints in the Reporting Month is tabulated in Table III.

 

9.      No Limit Level exceedance for day time construction noise monitoring were recorded in the reporting month. Detail shall refer to Appendix N.

 

Water Quality Monitoring

 

10.  Groundwater quality monitoring had been suspended since October 2019 upon the agreement by EPD. Further details should be founded at Section 4.1.

 

11.  No marine water quality monitoring is required as no marine works will be conducted at the Cha Kwo Ling and Lam Tin areas for this project.

 

12.  As the construction activity is approximately 120m away from the piezometer gate, no piezometer monitoring is required.


 

 

Waste Management 

 

13.  Wastes generated from this Project include inert construction and demolition (C&D) materials, and non-inert C&D materials. Details of waste management data is presented in Appendix H.

Ecological Monitoring

 

14.  No coral monitoring is required as no marine works will be conducted at the Cha Kwo Ling and Lam Tin areas for this project.

 

Fisheries Impact Monitoring

 

15.  No specific fisheries monitoring programme is required during the construction phase.

 

Monitoring on Cultural Heritage

 

16.  As the construction works of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to the TKOLTT at the Eastern Ventilation Building are located more than 100m away from the Cha Kwo Ling Tin Hau temple, no monitoring on cultural heritage is required.

 

Landscape and Visual Monitoring and Audit

 

17.  The implementation of landscape and visual mitigation measures was checked by a registered landscape architect. Recommended follow-up actions have been discharged by the Contractor.  Details of the audit findings and implementation status are presented in Section 12.

 

Landfill Gas Monitoring

 

18.  Monitoring of landfill gases was commenced in December 2016. Since no excavation activity for this Project was carried out within the Sai Tso Wan Landfill Consultation Zone in the reporting month, no landfill gas monitoring is required

 

Hazard to Life Monitoring

 

19.   No environmental monitoring and audit is required as no hazard assessment was conducted.

 

Environmental Site Inspection

 

20.  Joint weekly site inspections were conducted by representatives of the Contractor, Engineer and Environmental Team. Details of the audit findings and implementation status are presented in Section 12.


 

Key Information in the Reporting Month                                                                       

 

21.  Summary of key information in the reporting month is tabulated in Table II

                                                                                                                             

Table II    Summary of Complaints, Notifications of Summons and Successful Prosecutions in the Reporting Month

Event

Event Details

Action Taken

Status

Number

Nature

Complaints Received

1

Noise

Detail refer to App M

Closed

Notifications of any summons & prosecutions received

0

--

N/A

N/A

 

22.  Summary of complaints received in the reporting month is tabulated in Table III.

 

Table III     Summary of Complaints Details in Reporting Month

Complaint Type

Investigation Findings

Follow-up Action / Mitigation Measure

Noise nuisance generated from the construction activities at Portion T1 & V (6 September 2023)

The weekly noise monitoring and additional noise assessments have verified that the noise levels remain within the set limits. Moreover, the groundborne noise measurements data suggests that the noise levels are well within the criteria outlined in the TM.

According to the investigation

result, the construction

activities of Trunk Road T2

conducted inside the tunnel

area and the construction

activities of TKO-LT Tunnel

conducted inside the tunnel

section at Kwun Tong Side are

considered as one of the

potential noise source of the

ground borne noise nuisance

ˇP         A valid CNP was hold and construction activities being taken were complied with the relevant CNP

ˇP         The contractor has taken steps to address noise concerns by implementing noise control measures such as erecting noise barriers and using a hydraulic breaker equipped  with a noise muffler.

ˇP         In addition, the Contractor should still maintain good site practices, such as schedule noisy work to the less sensitive hours and provide regularly maintenance for PMEs.

ˇP         Contractor is recommended to continue to strictly follow the requirements in the relevant CNP and the approved CNMP.

ˇP         According to the condition 3.d point 5 of the CNP (GW-RE0973-23), the immediate remedial action shall be implemented in case adverse ground-borne noise impact on any noise sensitive receiver is received

 

 

 

 

 

 

Reporting Changes

23.  No reporting change is recorded in the reporting months.

 

Future Key Issues

 

24.  The key works or activities will be anticipated in the next reporting period are as follows:

 

 Table IV    Summary Table for Site Activities in the next Reporting Period

Site Activities (October 2023)

Key Environmental Issues

1.      East Bound ˇV RC Structure Construction, Lining, Bulkhead Construction.

2.       East Ventilation Building ˇV RC Structure.

3.       West Bound ˇV RC Structure Construction, Pilot Tunnel Excavation, Lining. 

(A) / (B) / (C) / (D)

Note:

(A)    Dust generation from haul road, stockpile of dusty materials, exposed site area, excavation works and rock breaking activities;

(B)    Noisy construction activity such as rock-breaking activities and piling works;

(C)    Runoff from exposed slope or site area; and

(D)    Wastewater and runoff discharge from site.


 

1.          INTRODUCTION

Background

1.1         In 2009, Civil Engineering and Development Department (CEDD) commissioned a Kai Tak Development (KTD) ˇV Trunk Road T2 and Infrastructure at South Apron Investigation. The assignment covers the provision of the Trunk Road T2 and its connections with the Central Kowloon Route (CKR) at the north apron area and the Tseung Kwan O ˇV Lam Tin Tunnel (TKOLTT) to the south in the Cha Kwo Ling area.

1.2         The Trunk Road T2 Project is one of the designated Projects under Schedule 2 of the EIAO proposed in the KTD. CEDD submitted the Project Profile (No. PP-379/2009) on 24 March 2009 for application for an EIA study brief for the Trunk Road T2 Project under the EIAO. Accordingly, an EIA Study Brief (ESB-203/2009) for the Trunk Road T2 Project was issued on 30 April 2009. The Environmental Impact Assessment (EIA) Report for the Trunk Road T2 Project was approved under the Environmental Impact Assessment Ordinance (EIAO) on 19 September 2013. The corresponding Environmental Permit (EP) was issued on 19 September 2013 (EP no.: EP-451/2013).

1.3         The Contract No. ED/2018/04 is the main contract of Trunk Road T2 (ˇ§T2 Main Worksˇ¨) which comprises mainly the design and construction of a dual two-lane trunk road of approximately 3.0km long with about 2.7km of the trunk road in form of tunnel; ventilation and administration buildings, environmental protection and mitigation works and etc. The EM&A programme under this Contract is governed by the two EPs (EP-451/2013 and EP-458/2013/C) and two EM&A Manuals (AEIAR-174/2013 and AEIAR-173/2013). The work areas of the T2 Main Works are shown in Figure 1 and the works to be executed under this Contract and corresponding EPs are summarized as follows:

Environmental Permit

Works Description

EP-451/2013 ˇV Trunk Road T2

Trunk Road T2

ˇ´    Construction of highway and sub-sea tunnel connecting between Central Kowloon Route and Cha Kwo Ling Tunnel

ˇ´    Western & Eastern Ventilation Buildings

EP-458/2013/C ˇV Tseung Kwan O ˇV Lam Tin Tunnel (TKOLTT) and Associated Works

Cha Kwo Ling Tunnel

Construction of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to the TKOLTT at the Eastern Ventilation Building

 

Monitoring Works in Lam Tin under EP-458/2013/C

1.4         Under Agreement No. CE 59/2015 (EP) ˇV Tseung Kwan O ˇV Lam Tin Tunnel (TKOLLT) and Associated Works, the baseline monitoring works in Lam Tin under the EM&A Manual (AEIAR-173/2013) were conducted by the Environmental Team (ET) for the Agreement No. CE 59/2015 (EP) at the approved monitoring locations, namely AM1, AM2, AM3, AM4, AM4 (A) CM1, CM2, CM3, CM4 and CM5. Impact monitoring within the Lam Tin area shall be conducted by the ET of Contract No. ED/2018/04 upon cessation of Agreement No. CE 59/2015 (EP). The data obtained from the impact monitoring works completed by the ET of Agreement No. CE 59/2015 (EP) will be adopted in this report.


 

1.5         Cinotech Consultants Ltd. was designated as the Environmental Team (ET) to undertake the EM&A works for ˇ§Trunk Road T2 and Infrastructure Works for Developments at the Former South Apronˇ¨ (hereinafter called the ˇ§Projectˇ¨). 

Purpose of the Report

1.6         This is the 41st Monthly EM&A Report which summarises the impact monitoring results and audit findings for the EM&A programme during the reporting period in September 2023.

Project Organizations

1.7         Different Parties with different levels of involvement in the Project organization include:

        Permit Holder ˇV Civil Engineering and Development Department  (CEDD)

        Supervisor Representative ˇV Hyder-Meinhardt Joint Venture (HMJV)

        Environmental Team (ET) ˇV Cinotech Consultants Limited (Cinotech)

        Independent Environmental Checker (IEC) ˇV Ramboll Hong Kong Limited (Ramboll)

        Contractor ˇV Bouygues Travaux Publics (BTP)

1.8         The key contacts of the Project are shown in Table 1.1.

Table 1.1       Key Project Contacts

Party

Role

Contact Person

Phone No.

CEDD

Permit Holder

Mr. Wong Chi Wai, Tommy

3842 7111

HMJV

Supervisor Representative

Ms. Hazel Tang

2149 8524

Cinotech

Environmental Team

Mr. KS Lee (ETL)

2151 2091

Ms. Karina Chan

2157 3880

Ramboll

Independent Environmental Checker

Mr. YH Hui

3465 2850

BTP

Contractor

Mr. Roy Leung

6628 2685

 

1.9         The Organizational Structure for Environmental Management is shown in Figure 1.2.

Construction Activities undertaken during the Reporting Month

1.10     The major site activities undertaken in the reporting month included:

        East Bound ˇV RC Structure Construction, Lining

        East Ventilation Building ˇV RC Structure.

        West Bound ˇVRC Structure Construction, Pilot Tunnel Excavation, Lining


 

Summary of EM&A Requirements

1.11     The EM&A programme requires construction noise, air quality monitoring and environmental site audit, etc. The EM&A requirements for each parameter are described in the following sections, including:

        All monitoring parameters;

        Action and Limit levels for all environmental parameters;

        Event Action Plans;

        Environmental mitigation measures, as recommended in the Project EIA Report.

1.12     The advice on the implementation status of environmental protection and pollution control/mitigation measures is summarized in Section 12 of this report.

1.13     This report presents the monitoring results, observations, locations, equipment, period, methodology and QA/QC procedures of the monitoring parameters of the required environmental monitoring works and audit works for the Project in September 2023.

Status of Environmental Licensing and Permitting

1.14     All permits/licenses obtained for the Project are summarized in Table 1.2.

Table 1.2      Summary of Environmental License and Permit

Permit / License No.

Valid Period

Status

From

To

Environmental Permit (EP)

EP-451/2013

19 Sep 2013

N/A

Valid

EP-458/2013/C

20 Jan 2017

N/A

Valid

Notification pursuant to Air Pollution (Construction Dust) Regulation

Ref. No.: 451120

20 Nov 2019

N/A

Valid

Billing Account for Construction Waste Disposal

A/C No.: 7036016

09 Dec 2019

N/A

Valid

Construction Noise Permit

CNP No. (For Portion Q): GW-RE0282-23

22 Mar 2023

21 Sep 2023

Expired on 21 Sep 2023

CNP No. (For Portion U): GW-RE1003-23

21 Aug 2023

20 Nov 2023

Valid

CNP No. (For Portion T1): GW-RE0973-23

1 Sep 2023

26 Sep 2023

Expired on 26 Sep 2023

CNP No. (For Portion Q):GW-RE1151-23

21 Sep 2023

20 Dec 2023

Valid

CNP No. (For Portion T1): GW-RE1182-23

27 Sep 2023

26 Dec 2023

Valid

Wastewater Discharge License

WT00036699-2020

14 Jan 2021

31 Jan 2026

Valid

Chemical Waste Producer License

WPN: 5213-286-B2557-03

09 Mar 2020

N/A

Valid


2.          NOISE

Monitoring Requirements

2.1         According to Section 3.2.1 of the EM&A Manual (AEIAR-173/2013), construction noise monitoring was conducted to monitor the construction noise arising from the construction activities. The regular monitoring frequency for each monitoring station shall be on a weekly basis and conduct one set of measurements between 0700 and 1900 hours on normal weekdays. Appendix A shows the established Action and Limit Levels for the environmental monitoring works.

Monitoring Locations

2.2         Noise monitoring was conducted at five designated monitoring stations, namely CM1, CM2, CM3, CM4 and CM5 in the reporting period. Table 3.1 and Figure 2 show the locations of these stations.

Table 3.1   Noise Monitoring Stations

Monitoring Stations

Location

Location of Measurement

CM1

Nga Lai House, Yau Lai Estate Phase 1, Yau Tong

Rooftop (41/F)

CM2

Bik Lai House, Yau Lai Estate Phase 1, Yau Tong

Rooftop (41/F)

CM3

Block S, Yau Lai Estate Phase 5, Yau Tong

Rooftop (40/F)

CM4

Tin Hau Temple, Cha Kwo Ling

Ground Level

CM5

CCC Kei Faat Primary School, Yau Tong

Rooftop (6/F)

 

Monitoring Parameters, Frequency and Duration

2.3         Table 3.2 summarizes the monitoring parameters, frequency and total duration of monitoring.  The noise monitoring schedule is shown in Appendix D.

         Table 3.2         Frequency and Parameters of Noise Monitoring

Monitoring Stations

Time Period

Duration

Frequency

Parameter

Measurement

CM1

0700-1900 hrs on normal weekdays

30 minutes

Once per week

L10(30 min.) dB(A)

 

L90(30 min.) dB(A)

 

Leq(30 min.) dB(A)

Façade Measurement

CM2

Façade Measurement

CM3

Façade Measurement

CM4

Façade Measurement

CM5

Façade Measurement

Monitoring Equipment

2.4         Integrating Sound Level Meter was used for impact noise monitoring. The meters were Type 1 sound level meter capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx) that also complied with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Table 3.3 summarizes the noise monitoring equipment being used by the ET for Agreement No. CE 59/2015 (EP) within the reporting period. Copies of calibration certificates are attached in Appendix B.

Table 3.3        Noise Monitoring Equipment

Equipment

Model

Quantity

Integrating Sound Level Meter

BSWA 308 (Serial No.: 580287, 570187,580238)

SWAN 957 (Serial No.: 21455),

SWAN 979 (Serial No.: 27189)

5

Calibrator

ST-120 (Serial No.: 181001637)

AWA6021A (Serial no. 1023253)

2

Monitoring Methodology and QA/QC Procedure

2.5         The monitoring procedures are as follows:

ˇ´            The monitoring station was normally be at a point 1m from the exterior of the sensitive receivers building façade and be at a position 1.2m above the ground.

ˇ´            For free field measurement, the meter was positioned away from any nearby reflective surfaces. All records for free field noise levels were adjusted with a correction of +3 dB(A).

ˇ´            The battery condition was checked to ensure the correct functioning of the meter.

ˇ´            Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:

-            Frequency weighting: A

-            Time weighting: Fast

-            Time measurement: 30 minutes

ˇ´            Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94.0 dB at 1000 Hz.  If the difference in the calibration level before and after measurement was more than 1.0 dB, the measurement would be considered invalid and repeat of noise measurement would be required after re-calibration or repair of the equipment.

ˇ´            The wind speed was frequently checked with the portable wind meter.

ˇ´            At the end of the monitoring period, the Leq, L90 and L10 were recorded.  In addition, site conditions and noise sources were recorded on a standard record sheet.

ˇ´            Noise monitoring would be cancelled in the presence of fog, rain, and wind with a steady speed exceeding 5 m/s, or wind with gusts exceeding 10 m/s. Supplementary monitoring would be provided to ensure sufficient data would be obtained.

Maintenance and Calibration

2.6         The microphone head of the sound level meter and calibrator were cleaned with a soft cloth at quarterly intervals.

2.7         The sound level meter and calibrator were checked and calibrated at yearly intervals.

2.8         Immediately prior to and following each noise measurement the accuracy of the sound level meter was checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements were accepted as valid only if the calibration levels from before and after the noise measurement agree to within 1.0 dB.

Results and Observations

2.9         The data obtained from the impact monitoring works completed by the ET of Agreement No. CE 59/2015 (EP) will be adopted in this report. 

2.10     One (1) Action Level exceedance was recorded due to the documented complaint in the reporting month.

2.11     No Limit Level exceedance was recorded for day-time construction noise monitoring in the reporting month.

2.12     Noise monitoring results and graphical presentations are shown in Appendix G.

2.13     According to field observations by ET for Agreement No. CE 59/2015 (EP) in the reporting period, the major noise sources identified at the noise monitoring stations are shown in Table 3.4.

Table 3.4       Other Noise Source Identified during Noise Monitoring

Monitoring Stations

Major Noise Source

CM1

Road Traffic near Eastern Cross Harbour Tunnel Toll Plaza, non-project related construction activities (i.e road paving work in TKOLTT project)

CM2

Road Traffic near Eastern Cross Harbour Tunnel Toll Plaza, non-project related construction activities  (i.e road paving work in TKOLTT project)

CM3

Road Traffic near Eastern Cross Harbour Tunnel Toll Plaza non-project related construction activities  (i.e road paving work in TKOLTT project)

CM4

Road Traffic at Cha Kwo Ling Road, non-project related construction activities  (i.e underground utility work in TKOLTT project)

CM5

Road Traffic near Eastern Cross Harbour Tunnel Toll Plaza,

Road Traffic at Yau Tong Road

                .

Table 3.5      Baseline Noise Level and Noise Limit Level for Monitoring Stations

Monitoring Stations

Baseline Noise Level, dB (A)
(at 0700 ˇV 1900 hrs on normal weekdays)

Noise Limit Level, dB (A) (at 0700 ˇV 1900 hrs on normal weekdays)

CM1

65.5

75

CM2

63.6

CM3

65.6

CM4

62.0

CM5

68.2

70*

(*) Noise Limit Level is 65 dB(A) during school examination periods.

 

Comparison of EM&A Result with EIA Prediction

2.14     The noise monitoring data was compared with the predictions in Table 4.15 of EIA Report (AEIAR-173/2013) as summarised in Table 3.6.

 

Table 3.6     Maximum Predicted Mitigated Construction Noise Levels in EIA Report

Monitoring Stations

NSR ID

Maximum Predicted Mitigated Construction Noise Levels in EIA Report (AEIAR-173/2013), dB(A)

Maximum Construction Noise Levels in the Reporting Month
 (September 2023),
Leq (30min) dB(A)

CM1 ˇV Nga Lai House, Yau Lai Estate Phase 1, Yau Tong

N1102

73

68.0

CM2 ˇV Bik Lai House, Yau Lai Estate Phase 1, Yau Tong

N1204

75

72.0

CM3 ˇV Block S, Yau Lai Estate Phase 5, Yau Tong

N2105

75

66.0

CM4 ˇV Tin Hau Temple, Cha Kwo Ling

N3101a

73

62.0

CM5 ˇV CCC Kei Faat Primary School, Yau Tong

N4101

71

68.0

 

2.15     The results at CM1, CM2, CM3, CM4 and CM5 were lower than the maximum predicted mitigated construction noise level in EIA Report, AEIAR-173/2013 (as approved in 2013). No Limit level exceedance was recorded in the reporting period.


 

3.          WATER QUALITY

Monitoring Requirement

Groundwater Quality

3.1         The existing groundwater quality monitoring programme has been suspended as the monitoring results had been deemed non-representative of the impact from the project justified by two major factors: (1) influence on the monitoring results from non-project related factors, such as anthropogenic activities and natural phenomenon; and (2) large separation between the monitoring stations and works area. In addition, as no alternative locations for the groundwater quality monitoring were available, the groundwater quality monitoring has been suspended since October 2019 upon the agreement by EPD.

Marine Water Quality

3.2         According to Section 4.4.3 of EM&A Manual (AEIAR-173/2013), marine water quality impact monitoring stations is carried out during marine construction for TKOLTT reclamation. Since the construction of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to the TKOLTT at the Eastern Ventilation Building does not involve reclamation, the marine water quality monitoring programme stated in Section 4.4 of the EM&A Manual (AEIAR-173/2013) is therefore not applicable to Contract No. ED/2018/04.

Groundwater Level Monitoring (Piezometer Monitoring)

3.3         According to Section 4.1.2 of EM&A Manual (AEIAR-173/2013), daily piezometer monitoring will be carried out on a daily basis when any tunnel construction activities are carried out within +/- 50m of the piezometer gate in plan. As the construction works of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to the TKOLTT at the Eastern Ventilation Building is approximately 120m away from the piezometer gate in plan, the piezometer monitoring programme stated in Section 4.2 of the EM&A Manual (AEIAR-173/2013) is therefore not applicable to Contract No. ED/2018/04.

 

4.          WASTE MANGEMENT

4.1         According to Section 5.1.2 of the EM&A Manual (AEIAR-173/2013), Waste materials generated during construction activities, such as construction and demolition (C&D) materials and general refuse, are recommended to be audited at regular intervals (at least quarterly) to ensure that proper storage, transportation and disposal practices are being implemented by the Contractor. To fulfil this requirement, site audits are carried out on a weekly basis. The summaries of site audits are attached in Appendix I.

4.2         With reference to relevant handling records of this Project, the quantities of different types of waste generated in the reporting month are summarised and presented in Appendix H.


 

5.          ECOLOGY

 

Post-Translocation Coral Monitoring

5.1         Post-translocation monitoring survey is recommended in Section 6.2.5 of the EM&A Manual (AEIAR-173/2013), to audit the success of coral translocation. Since the construction of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to the TKOLTT at the Eastern Ventilation Building does not involve any marine works in the concerned area mentioned in Section 6.1.2 of the EM&A Manual (AEIAR-173/2013), the post-translocation monitoring survey stated in Section 6.2.5 of the EM&A Manual (AEIAR-173/2013) is therefore not applicable to Contract No. ED/2018/04.

 

6.          FISHERIES

6.1         According to Section 7.1.3 of EM&A Manual (AEIAR-173/2013), no specific fisheries monitoring programme is required during the construction phase.

6.2         The implementation of the mitigation measures stated in the Water Quality Impact Assessment (Refer to Section 5 of EIA Report (AEIAR-173/2013)) will be audited as part of the EM&A procedures during the construction period. The summaries of site audits are attached in Appendix I.

 

7.          CULTURAL HERITAGE

7.1         According to Condition 3.7 of EP-458/2013/C and Section 8.2.1 of the EM&A Manual (AEIAR-173/2013), monitoring of vibration impacts was conducted when the construction works are less than 100m from the Built Heritage in close proximity of the worksite, namely the Cha Kwo Ling Tin Hau temple. Tilting and settlement monitoring should be applied on the Cha Kwo Ling Tin Hau Temple.

 

7.2         As the construction works of Cha Kwo Ling Tunnel from the end of Trunk Road T2 to the TKOLTT at the Eastern Ventilation Building are located more than 100m away from the Cha Kwo Ling Tin Hau temple, the vibration impact monitoring stated in Section 8.3.1 of the EM&A Manual (AEIAR-173/2013) is not applicable to Contract No. ED/2018/04.            

 

Mitigation Measures for Cultural Heritage

 

7.3         According to Condition 3.6 of EP-458/2013/C, to prevent damage to Cha Kwo Ling Tin Hau Temple and its Fung Shui rocks (Child-given rocks) during the construction phase, a temporarily fenced-off buffer zone (Rocks buffer zone is 5 m from the edge of Rocks and 15m from the edge of Rocks alter) with allowance for public access (minimum 1 m) around the temple and the Fung Shui rocks shall be provided. The open yard in front of the temple should be kept as usual for annual Tin Hau festival.

 

 

 

7.4         As there is a large buffer distance from the current works to Cha Kwo Ling Tin Hau Temple and the Fung Shui rocks (Child-given rocks), the temporarily fenced-off rocks buffer zone and from the edge of Rocks alter is not required. The fenced-off rocks buffer zone would be implemented when there is construction activities in vicinity of the cultural heritage.

 

8.          LANDSCAOPE AND VISUAL IMPACT

8.1         According to Section 9.3 of the EM&A Manual (AEIAR-173/2013), landscape and visual mitigation measures during the construction phase shall be checked to ensure that they are fully realized and implemented on site.

8.2         Site audits were carried out on a weekly basis to monitor and audit the timely implementation of landscape and visual mitigation measures listed in ˇ§Environmental Mitigation Implementation Schedule (EMIS)ˇ¨ (shown in Appendix J).

8.3         The implementation of landscape and visual mitigation measures was checked by a registered landscape architect. No non-compliance of the landscape and visual impact was recorded in the reporting month. Details of the audit findings and implementation status are presented in Appendix I.

 

9.          LANDFILL GAS MONITORING

Monitoring Requirement

9.1         In accordance with Section 10.1.1 of the EM&A Manual (AEIAR-173/2013), monitoring of landfill gas is required for construction works within the Sai Tso Wan Landfill Consultation Zone during the construction phase. Since no excavation activity for this Project was carried out within the Sai Tso Wan Landfill Consultation Zone in the reporting month, no landfill gas monitoring is required.

10.      HAZARD TO LIFE

 

10.1     According to Section 11.1.1 of EM&A Manual (AEIAR-173/2013), as no overnight storage of explosive on site is required for the construction of the Project, the hazard assessment is deemed not necessary. Thus, environmental monitoring and audit is not required.


 

11.      ENVIRONEMNTAL AUDIT

Site Audits

11.1     Site audits were carried out on a weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Project site.  The summaries of site audits are attached in Appendix I. 

11.2     Site audits were conducted on 07, 14, 21 & 28 September 2023 in the reporting month. Site inspection of the IEC was conducted on 28 September 2023. No non-compliance was observed during the site audit.

Implementation Status of Environmental Mitigation Measures

11.3     According to Environmental Permits, the approved EIA Reports (Register No.: AEIAR-174/2013 and AEIAR-173/2013), and the EM&A Manuals of the Project (AEIAR-174/2013 and AEIAR-173/2013), the mitigation measures detailed in the documents are recommended to be implemented during the construction phase.  An Environmental Mitigation Implementation Schedule (EMIS) is provided in Appendix J.

11.4     The ET weekly site inspections were carried out during the reporting month and the observations and recommendations are summarized in Table 12.1. Refer to Appendix I for the site inspection summary reports in the reporting month.

Table 12.1    Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Air Quality

31 August 2023

Water spraying should be provided to the haul road to avoid dust generation.

The contractor had sprayed the water along the haul road to avoid dust generation.

7 September 2023

Water spraying should be applied when conducting dust-generating activities. 

The water sprinkler installed near the unloading area of the PTBM.

28 September 2023

Water spraying should be applied along the haul road near the site entrance (Westbound tunnel).

To be reported in the next reporting month.

Noise

N/A

There was no observation in the reporting period.

N/A

Water Quality

N/A

There was no observation in the reporting period.

N/A

Ecology

N/A

There was no observation in the reporting period.

N/A

Landscape and Visual

N/A

There was no observation in the reporting period.

N/A

Waste/ Chemical Management

21 September 2023

Drip tray should be provided for chemical containers to prevent chemical leakage. 

Contractor had removed the chemical containers.

Permits /Licences

N/A

There was no observation in the reporting period.

N/A

   Implementation Status of Event and Action Plans

11.5     The Event and Action Plans for air quality and construction noise monitoring, and the Limit Levels and Action Plan for landfill gas monitoring are presented in Appendix L.

Air Quality Monitoring

ˇ´        No Action/Limit Level exceedance for 1-hour TSP monitoring was recorded in the reporting month.

ˇ´        No Action Level exceedance for 24-hour TSP monitoring was recorded in the reporting month and no Limit Level exceedance for 24-hour TSP monitoring was recorded in the reporting month.

 

               Construction Noise Monitoring

ˇ´       One (1) Action Level exceedance was recorded due to the documented complaint in the reporting month.

ˇ´       No Limit Level exceedance for construction noise monitoring was recorded in the reporting month.

12.      ENVIRONMENTAL NON-COMFORMANCE

Summary of Complaint, Warning, Notification of any Summons and Successful Prosecution

12.1     The summaries of environmental complaint, warning, summon and notification of successful prosecution for the Project is presented in Appendix M.

Summary of Exceedance

12.2     The summary of exceedance record in the reporting month is shown in Appendix N.

13.      FUTURE KEY ISSUES

13.1     Tentative construction programmes for the next three months are provided in Appendix O.

13.2     Major site activities undertaken for the coming months are summarized as follows:

        East Bound ˇV RC Structure Construction, Lining, Bulkhead Construction

        East Ventilation Building ˇVRC Structure.

        West Bound ˇVRC Structure Construction, Pilot Tunnel Excavation, Lining.

 

13.3     Key environmental issues in the coming months include:

        Make sure noise mitigation measures are implemented accordingly;

        Make sure drainage system is adequately designed to prevent flooding during periods of heavy rain; and,

        Make sure mitigation measure for dust suppression are implemented on site

 

Monitoring Schedule

13.4     The tentative environmental monitoring schedule for the next month is shown in Appendix D.


14.      CONCLUSION AND RECOMMENDATION

Conclusions

14.1     This is the 41st Monthly EM&A Report which presents the EM&A works undertaken during the reporting month in accordance with the EM&A Manual (AEIAR-173/2013) and the requirement under EP.

Air Quality Monitoring

14.2     No Action/Limit Level exceedance was recorded for 1-hour TSP monitoring in the reporting month.

14.3     No Action Level exceedance for 24-hour TSP monitoring was recorded in the reporting month and no Limit Level exceedance for 24-hour TSP monitoring was recorded in the reporting month.

Construction Noise Monitoring 

14.4     One (1) Action Level exceedance was recorded due to documented complaint in the reporting month.

14.5     No Limit Level exceedance for construction noise monitoring was recorded in the reporting month.

Site Audit                     

14.6      4 ET joint weekly environmental site inspections were conducted in the reporting month.

Complaint, Notification of Summons and Successful Prosecution

14.7     One (1) environmental complaint was received in the reporting period. No notifications of summons and successful prosecutions were received in the reporting month.

Recommendations

14.8     According to the environmental audit performed in the reporting month, the following recommendations were made:

Air quality:.

ˇ´       Water spraying should be applied when conducting dust-generating activities.

Waste/ Chemical Management.

ˇ´       The drip tray should be provided for the chemical container to avoid the chemical leakage.